7234 N MILWOOD AVE 91303
Certificate Information: 7234 N MILWOOD AVE 91303
- Application / Permit
- 20016-10000-01395
- Plan Check / Job No.
- B20LA00866
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- E-plan Soft-Story seismic retrofit per LABC Chapter 93: Seismic reinforcement of parking garage using (2) special cantilevered columns with grade beams
- Permit Issued
- Issued on 3/18/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 12/4/2020
Permit Application Status History
| Submitted | 1/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/5/2020 | DANIEL YIP |
| Corrections Issued | 2/11/2020 | DANIEL YIP |
| Quality Review Completed | 2/23/2020 | HANS SANTIAGO |
| Plan Check Approved | 3/2/2020 | DANIEL YIP |
| Issued | 3/18/2020 | LADBS |
| OK for CofC | 12/4/2020 | ERNESTO CORRAL |
| CofC Issued | 12/4/2020 | ERNESTO CORRAL |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 3/10/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Repipe 1 Restoration Inc; Lic. No.: 1003868-B | , |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/27/2020 | Corrections Issued | JONATHAN QUACH |
| Footing/Foundation/Slab | 4/22/2020 | Approved | DANIEL VARNUM |
| Structural Steel Frame | 4/22/2020 | Approved | DANIEL VARNUM |
| Wood Frame | 4/22/2020 | Approved | DANIEL VARNUM |
| Deputy Reinf. Concrete | 4/23/2020 | Conditional Approval | DANIEL VARNUM |
| Deputy Steel/Welding | 4/23/2020 | Conditional Approval | JEFFREY DURAN |
| Structural Steel Frame | 4/30/2020 | Approved | DANIEL VARNUM |
| Wood Frame | 4/30/2020 | Approved | DANIEL VARNUM |
| Interior/Exterior Lathing | 5/8/2020 | Approved | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 7/30/2020 | SGSOV Not Ready | DANIEL VARNUM |
| Final | 8/7/2020 | Not Ready for Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 8/7/2020 | SGSOV Not Ready | DANIEL VARNUM |
| Smoke Detectors | 8/7/2020 | Approved | DANIEL VARNUM |
| Final | 8/21/2020 | Partial Approval | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 8/21/2020 | SGSOV Approved | DANIEL VARNUM |
| Final | 12/4/2020 | OK for CofC | ERNESTO CORRAL |