4510 N HAZELTINE AVE 91423
Certificate Information: 4510 N HAZELTINE AVE 91423
- Application / Permit
- 20016-10000-01235
- Plan Check / Job No.
- B20LA00745
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY SEISMIC RETROFIT AS PER DIV. 93, - USING (2) STEEL CANTILEVER COLUMN SYSTEM.
- Permit Issued
- Issued on 4/15/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 8/7/2020
Permit Application Status History
| Submitted | 1/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/22/2020 | YOUNG KIM |
| Corrections Issued | 1/25/2020 | YOUNG KIM |
| Quality Review Completed | 1/27/2020 | SAI KHUM |
| Building Plans Picked Up | 1/28/2020 | APPLICANT |
| Applicant returned to address corrections | 2/13/2020 | YOUNG KIM |
| Plan Check Approved | 3/10/2020 | YOUNG KIM |
| Issued | 4/15/2020 | LADBS |
| OK for CofC | 7/29/2020 | VAHE KELEDJIAN |
| CofC Issued | 8/7/2020 | ERNESTO CORRAL |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 3/18/2020 | PHILLIP MUNGUIA |
Contact Information
| No Data Available. |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 5/21/2020 | No Access for Inspection | JOE VELASQUEZ |
| Pre-Inspection | 5/26/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Excavation/Setback/Form/Re-Bar | 6/8/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Excavation/Setback/Form/Re-Bar | 6/10/2020 | Corrections Issued | DANIEL VARNUM |
| Excavation/Setback/Form/Re-Bar | 6/11/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 6/23/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 6/25/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 6/30/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 7/7/2020 | Approved | JOE VELASQUEZ |
| Insulation | 7/15/2020 | Approved | JOE VELASQUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2020 | Partial Approval | JOE VELASQUEZ |
| Interior/Exterior Lathing | 7/23/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Interior/Exterior Lathing | 7/24/2020 | Approved | JOE VELASQUEZ |
| Final | 7/29/2020 | OK for CofC | VAHE KELEDJIAN |
| SGSOV-Seismic Gas S/O Valve | 7/29/2020 | SGSOV Approved | VAHE KELEDJIAN |
| Smoke Detectors | 7/29/2020 | Approved | VAHE KELEDJIAN |