4360 N TUJUNGA AVE 91604

Certificate Information: 4360 N TUJUNGA AVE 91604

Application / Permit
20016-10000-00958
Plan Check / Job No.
B20LA00575
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
CHANGE OF USE FROM SFD/RESTAURANT TO RESTAURANT. SCOPE OF WORK INCLUDE ADDITION AT THE SIDE TO INCLUDE TRELLIS. RESTRIPE REAR PARKING LOT. 1 OF 2
Permit Issued
Issued on 6/25/2024
Issuing Office
Metro
Current Status
CofO Issued on 9/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/13/2020 APPLICANT
Disabled Access Plans Picked Up 2/4/2020 APPLICANT
Assigned to Plan Check Engineer 2/7/2020 MICHAEL LOPEZ
Corrections Issued 2/10/2020 MICHAEL LOPEZ
Quality Review Completed 2/14/2020 QUAN NGHIEM
Building Plans Picked Up 2/19/2020 APPLICANT
Applicant returned to address corrections 6/30/2020 MICHAEL LOPEZ
Applicant returned to address corrections 7/15/2020 MICHAEL LOPEZ
Applicant returned to address corrections 11/9/2021 MICHAEL LOPEZ
Applicant returned to address corrections 11/23/2021 MICHAEL LOPEZ
Applicant returned to address corrections 3/1/2022 SALVADOR QUINTANILLA
Applicant returned to address corrections 9/15/2022 MICHAEL LOPEZ
Applicant returned to address corrections 10/19/2022 YOUNG KIM
Applicant returned to address corrections 8/29/2023 MICHAEL LOPEZ
Applicant returned to address corrections 6/12/2024 MICHAEL LOPEZ
Plan Check Approved 6/14/2024 MICHAEL LOPEZ
No Progress 6/14/2024 MICHAEL LOPEZ
Plan Check Approved 6/24/2024 MICHAEL LOPEZ
Issued 6/25/2024 APPLICANT
CofO in Progress 9/30/2025 ROBERT DAVIS
Permit Finaled 9/30/2025 JEFFREY DURAN
CofO Issued 9/30/2025 JEFFREY DURAN
Permit Finaled 9/30/2025 JEFFREY DURAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/17/2020 GUILLERMO PETRA
ZA Case Cleared 8/18/2020 KENTON TRINH
"Q" conditions Cleared 8/20/2020 KENTON TRINH
Sewer availability Cleared 8/20/2020 GUILLERMO PETRA
DAS Clearance Cleared 1/7/2021 MICHAEL LOPEZ
ZA Case Cleared 2/17/2021 BRYANT WU
ZI Cleared 2/24/2021 KENTON TRINH
Food Service Establishment Cleared 4/8/2021 PAWAN VERMA
Fire Marshall Fire Life Safety Cleared 8/24/2021 VIDAL GARCIA
Food establishment approval Cleared 11/9/2021 LACDHS APPROVED
Miscellaneous Cleared 8/18/2022 MARITZA PRZEKOP
Mechanical Car Lift Cleared 2/21/2024 VIDAL GARCIA
Demo/Removal of Rental Units Cleared 6/21/2024 AMANDA POSTMAN

Contact Information

Architect Little,, Lisa Kaye; Lic. No.: C32748 505 W PICO BLVD      LOS ANGELES, CA 90015
Contractor Ravello Construction; Lic. No.: 1068657-B 8322 BEVERLY BLVD STE 301      LOS ANGELES, CA 90048
Engineer Chikhale,, Jonathan William; Lic. No.: C78893 2820 MILITARY AVENUE      LOS ANGELES, CA 90064

Inspector Information

JEFFREY FULTON, (818) 374-1132 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/28/2024 Partial Inspection DEANDRE HOFFMAN
Excavation/Setback/Form/Re-Bar 7/3/2024 Approved KENNETH ROBERTS
Reinforced Masonry Frame 7/5/2024 Partial Approval KENNETH ROBERTS
Footing/Foundation/Slab 7/11/2024 Not Ready for Inspection STEVEN LEVITT
Light Gage Steel Frame 7/30/2024 Partial Inspection ANDREW DORSO
Drywall Nailing 7/31/2024 Approved STEVEN LEVITT
Interior/Exterior Lathing 8/2/2024 Approved STEVEN LEVITT
Footing/Foundation/Slab 8/13/2024 Corrections Issued DANNY RODRIGUEZ
Footing/Foundation/Slab 8/15/2024 Partial Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 8/19/2024 Not Ready for Inspection STEVEN LEVITT
Masonry Wall/Backfill 8/20/2024 Approved STEVEN LEVITT
Pre-Inspection 9/6/2024 Conditional Approval STEVEN LEVITT
Wood Frame 9/6/2024 Conditional Approval STEVEN LEVITT
Wood Frame 9/13/2024 Approved STEVEN LEVITT
Special/Order Compliance 9/17/2024 Approved STEVEN LEVITT
Final 4/1/2025 Not Ready for Inspection KENNETH ROBERTS
Footing/Foundation/Slab 4/1/2025 Approved KENNETH ROBERTS
SGSOV-Seismic Gas S/O Valve 4/1/2025 SGSOV Approved KENNETH ROBERTS
Smoke Detectors 4/1/2025 Approved KENNETH ROBERTS
Final 7/17/2025 Partial Approval KENNETH ROBERTS
Final 9/9/2025 Partial Inspection ROBERT DAVIS
Final 9/30/2025 OK to Issue CofO ROBERT DAVIS