1120 S ORANGE DR 90019

Certificate Information: 1120 S ORANGE DR 90019

Application / Permit
20016-10000-00850
Plan Check / Job No.
B20LA00538
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER LABC CHAPTER 93 INSTALL (4) STEEL SPECIAL CANTILEVER COLUMNS.
Permit Issued
Issued on 8/19/2020
Issuing Office
Valley
Current Status
CofC Issued on 3/5/2021

Permit Application Status History

Submitted 1/10/2020 APPLICANT
Assigned to Plan Check Engineer 1/29/2020 THOMAS SHERMAN
Corrections Issued 2/6/2020 THOMAS SHERMAN
Quality Review Completed 2/10/2020 SAI KHUM
Building Plans Picked Up 2/21/2020 APPLICANT
Applicant returned to address corrections 3/6/2020 THOMAS SHERMAN
Plan Check Approved 3/27/2020 THOMAS SHERMAN
Issued 8/19/2020 APPLICANT
OK for CofC 3/2/2021 MARK FERRARI
CofC Issued 3/5/2021 ERNESTO CORRAL

Permit Application Clearance Information

HPOZ Cleared 3/19/2020 DANIEL MATA
Tenant Habitability Plan Cleared 6/29/2020 MICHAEL SOTO

Contact Information

Contractor Green Home Development & Remodeling Inc; Lic. No.: 1031586-B 6501 SAUSALITO AVE      WEST HILLS, CA 91307
Engineer Mina,, Joseph Wadie; Lic. No.: C53465 7247 DARNOCH WY      WEST HILLS, CA 91307

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/25/2020 Approved DARRYL ARNOLD
Deputy Steel/Welding 10/9/2020 Conditional Approval TIMOTHY BUXTON
Deputy Drilled-In Anchors 11/5/2020 Conditional Approval DARRYL ARNOLD
Excavation/Setback/Form/Re-Bar 11/19/2020 Approved JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 11/19/2020 Not Ready for Inspection JONATHAN QUACH
Footing/Foundation/Slab 11/19/2020 Approved JONATHAN QUACH
Structural Steel Frame 11/19/2020 Partial Approval JONATHAN QUACH
Wood Frame 11/19/2020 Corrections Issued JONATHAN QUACH
Deputy Reinf. Concrete 11/30/2020 Conditional Approval DARRYL ARNOLD
Floor/Roof Diaphrgm/Shear Wall 12/1/2020 Conditional Approval JONATHAN QUACH
Insulation 12/1/2020 Approved JONATHAN QUACH
Structural Steel Frame 12/1/2020 Approved JONATHAN QUACH
Wood Frame 12/1/2020 Approved JONATHAN QUACH
Deputy Wood Construction 12/3/2020 Conditional Approval DARRYL ARNOLD
Interior/Exterior Lathing 12/9/2020 Approved DARRYL ARNOLD
Final 12/30/2020 Not Ready for Inspection DARRYL ARNOLD
METHANE-Final 12/30/2020 Conditional Approval DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 12/30/2020 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 12/30/2020 Conditional Approval DARRYL ARNOLD
Final 1/6/2021 Corrections Issued JONATHAN QUACH
METHANE-Final 1/6/2021 Approved JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 1/6/2021 SGSOV Not Ready JONATHAN QUACH
Smoke Detectors 1/6/2021 Approved JONATHAN QUACH
Final 1/29/2021 Not Ready for Inspection JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 1/29/2021 SGSOV Approved JONATHAN QUACH
Final 2/11/2021 Partial Approval DARRYL ARNOLD
Final 2/22/2021 Not Ready for Inspection DARRYL ARNOLD
Final 3/2/2021 OK for CofC MARK FERRARI