1233 S WESTERN AVE 90006
Certificate Information: 1233 S WESTERN AVE 90006
- Application / Permit
- 20016-10000-00614
- Plan Check / Job No.
- B20LA00336
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- TI and change of use for portion of building from retail/take out restraunt to office with (w) accessible restrooms and ramp. 10,400 sf office.
- Permit Issued
- Issued on 7/22/2020
- Issuing Office
- Current Status
- CofO Issued on 2/26/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2020 | SAM CHANG |
| Corrections Issued | 2/11/2020 | SAM CHANG |
| Disabled Access Plans Picked Up | 2/12/2020 | APPLICANT |
| Quality Review Completed | 2/26/2020 | ARMEN JIVALAGIAN |
| Building Plans Picked Up | 2/27/2020 | APPLICANT |
| Green Plans Picked Up | 5/4/2020 | APPLICANT |
| Applicant returned to address corrections | 5/21/2020 | SAM CHANG |
| Plan Check Approved | 6/30/2020 | SAM CHANG |
| Issued | 7/22/2020 | APPLICANT |
| CofO in Progress | 2/25/2021 | TIMOTHY BUXTON |
| CofO Issued | 2/26/2021 | ERNESTO CORRAL |
| Permit Finaled | 2/26/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2020 | CELINA MORENO |
| Sewer availability | Cleared | 3/10/2020 | CELINA MORENO |
| ZI | Cleared | 3/10/2020 | DAVID URITA |
| ZI | Cleared | 3/10/2020 | DAVID URITA |
| DAS Clearance | Cleared | 4/23/2020 | SOMKIAT SUPANYACHOTSKUL |
| Green Code | Cleared | 5/1/2020 | KHEDER ALRAZAA |
Contact Information
| Contractor | Sierra Pacific Constructors Inc; Lic. No.: 433163-B | 22212 VENTURA BLVD WOODLAND HILLS, CA 91364 |
| Engineer | Youssef,, Nabih Fouad Guirg; Lic. No.: S2026 | 550 S HOPE ST STE 1700 LOS ANGELES, CA 90071 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/28/2020 | Approved | TIMOTHY BUXTON |
| Deputy Reinf. Concrete | 7/29/2020 | Conditional Approval | TIMOTHY BUXTON |
| Light Gage Steel Frame | 8/10/2020 | Partial Inspection | JONATHAN QUACH |
| Green Building Rough | 8/14/2020 | Approved | TIMOTHY BUXTON |
| Light Gage Steel Frame | 8/14/2020 | Approved | TIMOTHY BUXTON |
| T-Bar Ceiling | 9/15/2020 | Approved | TIMOTHY BUXTON |
| Final | 10/2/2020 | Not Ready for Inspection | TIMOTHY BUXTON |
| Green Building Final | 10/2/2020 | Approved | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 10/2/2020 | SGSOV No Gas | TIMOTHY BUXTON |
| Smoke Detectors | 10/2/2020 | Approved | TIMOTHY BUXTON |
| Wood Frame | 10/2/2020 | Approved | TIMOTHY BUXTON |
| Final | 10/6/2020 | Conditional Approval | TIMOTHY BUXTON |