5330-5334 N RIVERTON AVE 91601
Certificate Information: 5330-5334 N RIVERTON AVE 91601
- Application / Permit
- 20016-10000-00537
- Plan Check / Job No.
- B20LA00290
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. INSTALL 2 SCCS.
- Permit Issued
- Issued on 4/7/2021
- Issuing Office
- Current Status
- CofC Issued on 10/27/2021
Permit Application Status History
| Submitted | 1/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/22/2020 | BIDYUT RATH |
| Corrections Issued | 1/30/2020 | BIDYUT RATH |
| Quality Review Completed | 2/5/2020 | SAI KHUM |
| Building Plans Picked Up | 2/7/2020 | APPLICANT |
| Plan Check Approved | 3/10/2020 | BIDYUT RATH |
| Issued | 4/7/2021 | APPLICANT |
| OK for CofC | 8/31/2021 | KENNETH ROBERTS |
| CofC Issued | 10/27/2021 | KENNETH ROBERTS |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 3/10/2020 | GRACIELA ACOSTA |
| Redevelopment Project Area | Cleared | 3/10/2020 | GRACIELA ACOSTA |
| Tenant Habitability Plan | Cleared | 4/7/2021 | MICHAEL SOTO |
Contact Information
| Contractor | Seismic Retrofit Solutions Inc; Lic. No.: 1023483-B | 16060 VENTURA BLVD STE 148 ENCINO, CA 91436 |
| Engineer | Tajvidi,, Seyed Mohammad; Lic. No.: C84559 | 9163 LEROY STREET SAN GABRIEL, CA 91775 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/7/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Pre-Inspection | 5/10/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 5/27/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 5/27/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 5/27/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 5/28/2021 | Approved | JOE VELASQUEZ |
| Structural Steel Frame | 5/28/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 5/28/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 6/1/2021 | Approved | HAMID PISHEHVAR |
| Wood Frame | 6/1/2021 | Approved | HAMID PISHEHVAR |
| Insulation | 6/2/2021 | Approved | JOE VELASQUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2021 | Approved | JOE VELASQUEZ |
| Interior/Exterior Lathing | 7/16/2021 | Approved | JOE VELASQUEZ |
| Final | 7/29/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| METHANE-Final | 7/29/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 7/29/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 7/29/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 8/9/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| METHANE-Final | 8/9/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 8/9/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 8/9/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 8/19/2021 | Partial Approval | KENNETH ROBERTS |
| METHANE-Final | 8/19/2021 | Approved | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 8/19/2021 | SGSOV Approved | KENNETH ROBERTS |
| Smoke Detectors | 8/19/2021 | Approved | KENNETH ROBERTS |
| Final | 8/31/2021 | OK for CofC | KENNETH ROBERTS |