5330-5334 N RIVERTON AVE 91601

Certificate Information: 5330-5334 N RIVERTON AVE 91601

Application / Permit
20016-10000-00537
Plan Check / Job No.
B20LA00290
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER LABC CH. 93. INSTALL 2 SCCS.
Permit Issued
Issued on 4/7/2021
Issuing Office
Current Status
CofC Issued on 10/27/2021

Permit Application Status History

Submitted 1/8/2020 APPLICANT
Assigned to Plan Check Engineer 1/22/2020 BIDYUT RATH
Corrections Issued 1/30/2020 BIDYUT RATH
Quality Review Completed 2/5/2020 SAI KHUM
Building Plans Picked Up 2/7/2020 APPLICANT
Plan Check Approved 3/10/2020 BIDYUT RATH
Issued 4/7/2021 APPLICANT
OK for CofC 8/31/2021 KENNETH ROBERTS
CofC Issued 10/27/2021 KENNETH ROBERTS

Permit Application Clearance Information

Historic Resource Verification Cleared 3/10/2020 GRACIELA ACOSTA
Redevelopment Project Area Cleared 3/10/2020 GRACIELA ACOSTA
Tenant Habitability Plan Cleared 4/7/2021 MICHAEL SOTO

Contact Information

Contractor Seismic Retrofit Solutions Inc; Lic. No.: 1023483-B 16060 VENTURA BLVD STE 148      ENCINO, CA 91436
Engineer Tajvidi,, Seyed Mohammad; Lic. No.: C84559 9163 LEROY STREET      SAN GABRIEL, CA 91775

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/7/2021 Not Ready for Inspection JOE VELASQUEZ
Pre-Inspection 5/10/2021 Not Ready for Inspection JOE VELASQUEZ
Footing/Foundation/Slab 5/27/2021 Not Ready for Inspection JOE VELASQUEZ
Structural Steel Frame 5/27/2021 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 5/27/2021 Not Ready for Inspection JOE VELASQUEZ
Footing/Foundation/Slab 5/28/2021 Approved JOE VELASQUEZ
Structural Steel Frame 5/28/2021 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 5/28/2021 Not Ready for Inspection JOE VELASQUEZ
Structural Steel Frame 6/1/2021 Approved HAMID PISHEHVAR
Wood Frame 6/1/2021 Approved HAMID PISHEHVAR
Insulation 6/2/2021 Approved JOE VELASQUEZ
Floor/Roof Diaphrgm/Shear Wall 6/17/2021 Approved JOE VELASQUEZ
Interior/Exterior Lathing 7/16/2021 Approved JOE VELASQUEZ
Final 7/29/2021 Not Ready for Inspection JOE VELASQUEZ
METHANE-Final 7/29/2021 Not Ready for Inspection JOE VELASQUEZ
SGSOV-Seismic Gas S/O Valve 7/29/2021 SGSOV Not Ready JOE VELASQUEZ
Smoke Detectors 7/29/2021 Not Ready for Inspection JOE VELASQUEZ
Final 8/9/2021 Not Ready for Inspection JOE VELASQUEZ
METHANE-Final 8/9/2021 Not Ready for Inspection JOE VELASQUEZ
SGSOV-Seismic Gas S/O Valve 8/9/2021 SGSOV Not Ready JOE VELASQUEZ
Smoke Detectors 8/9/2021 Not Ready for Inspection JOE VELASQUEZ
Final 8/19/2021 Partial Approval KENNETH ROBERTS
METHANE-Final 8/19/2021 Approved KENNETH ROBERTS
SGSOV-Seismic Gas S/O Valve 8/19/2021 SGSOV Approved KENNETH ROBERTS
Smoke Detectors 8/19/2021 Approved KENNETH ROBERTS
Final 8/31/2021 OK for CofC KENNETH ROBERTS