3854 S INGLEWOOD BLVD 90066
Certificate Information: 3854 S INGLEWOOD BLVD 90066
- Application / Permit
- 20016-10000-00356
- Plan Check / Job No.
- B20LA00213
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan 1651 :: Soft-Story seismic retrofit per LABC Chapter 93: USING (3) SPECIAL CANTILEVERED COLUMNS WITH GRADE BEAMS.
- Permit Issued
- Issued on 5/19/2020
- Issuing Office
- Current Status
- Issued on 5/19/2020
Permit Application Status History
| Submitted | 1/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/29/2020 | DANIEL YIP |
| Corrections Issued | 2/5/2020 | DANIEL YIP |
| Quality Review Completed | 2/13/2020 | HANS SANTIAGO |
| Applicant returned to address corrections | 3/18/2020 | DANIEL YIP |
| Applicant returned to address corrections | 4/6/2020 | DANIEL YIP |
| Plan Check Approved | 5/1/2020 | DANIEL YIP |
| Issued | 5/19/2020 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/2/2020 | TORI CHEN |
| Tenant Habitability Plan | Cleared | 5/15/2020 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Retrofitting360 Inc; Lic. No.: 1039226-B | 19562 VENTURA BLVD# 230 TARZANA, CA 91356 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/2/2020 | Approved | SORIN CIRSTOIU |
| Footing/Foundation/Slab | 7/15/2020 | Approved | GRANT WOODS |
| Reinforced Concrete Frame | 7/15/2020 | Not Ready for Inspection | GRANT WOODS |
| Structural Steel Frame | 7/15/2020 | Not Ready for Inspection | GRANT WOODS |
| Wood Frame | 7/15/2020 | Not Ready for Inspection | GRANT WOODS |
| Deputy Steel/Welding | 7/16/2020 | Conditional Approval | GRANT WOODS |
| Reinforced Concrete Frame | 7/20/2020 | Not Ready for Inspection | GRANT WOODS |
| Structural Steel Frame | 7/20/2020 | Approved | GRANT WOODS |
| Wood Frame | 7/20/2020 | Approved | GRANT WOODS |
| Reinforced Concrete Frame | 7/30/2020 | Not Ready for Inspection | GRANT WOODS |
| Structural Steel Frame | 7/30/2020 | Approved | GRANT WOODS |
| Wood Frame | 7/30/2020 | Approved | GRANT WOODS |
| Interior/Exterior Lathing | 8/6/2020 | Approved | GRANT WOODS |
| Final | 8/11/2020 | Conditional Approval | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 8/11/2020 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 8/11/2020 | Approved | GRANT WOODS |
| Final | 8/25/2020 | Not Ready for Inspection | GRANT WOODS |