11754 W TENNESSEE AVE 90064

Certificate Information: 11754 W TENNESSEE AVE 90064

Application / Permit
20016-10000-00311
Plan Check / Job No.
B20LA00182
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION ONLY OF DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. WORK PER ENGINEER DESIGN.
Permit Issued
Issued on 6/23/2020
Issuing Office
Current Status
CofO Issued on 5/14/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/6/2020 APPLICANT
Assigned to Plan Check Engineer 1/6/2020 GEORGE ALVAREZ
Corrections Issued 1/6/2020 GEORGE ALVAREZ
Plan Check Approved 1/30/2020 KEVIN MORALES
Issued 6/23/2020 APPLICANT
CofO in Progress 5/14/2021 KENNETH NAGLE
Permit Finaled 5/14/2021 KENNETH NAGLE
CofO Issued 5/14/2021 KENNETH NAGLE
Permit Finaled 5/14/2021 KENNETH NAGLE

Permit Application Clearance Information

Address approval Cleared 1/27/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 1/27/2020 CELINA MORENO
Sewer availability Cleared 1/27/2020 CELINA MORENO
Specific Plan Cleared 1/27/2020 ANNA VIDAL
ZA Case Cleared 1/27/2020 ANNA VIDAL
Specific Plan Cleared 1/28/2020 DYLAN SITTIG

Contact Information

Contractor Mardyks & Co Inc; Lic. No.: 1025120-B 3923 REDWOOD AVENUE      LOS ANGELES, CA 90066
Engineer Nguyen,, Quynh Anh; Lic. No.: C58592 12000 MIRANDA ST      VALLEY VILLAGE, CA 91607

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 8/11/2020 Partial Approval OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 8/26/2020 Partial Approval OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 9/1/2020 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 10/6/2020 Corrections Issued OGANES TARAKHCHYAN
Deputy Wood Construction 10/14/2020 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 10/20/2020 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 10/23/2020 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 11/6/2020 Approved OGANES TARAKHCHYAN
HVAC-Rough 11/6/2020 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 11/23/2020 Partial Approval OGANES TARAKHCHYAN
Insulation 12/28/2020 Approved OGANES TARAKHCHYAN
Drywall Nailing 1/12/2021 Approved OGANES TARAKHCHYAN
Insulation 1/12/2021 Approved OGANES TARAKHCHYAN
Shower Pan 1/25/2021 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 1/28/2021 Approved OGANES TARAKHCHYAN
Gas Test 3/16/2021 Approved KENNETH NAGLE
BUILDING-Rough-Frame 4/20/2021 Approved KENNETH NAGLE
ELECTRICAL-Final 4/20/2021 Not Ready for Inspection KENNETH NAGLE
Final 4/20/2021 Corrections Issued KENNETH NAGLE
Green Building Final 4/20/2021 Not Ready for Inspection KENNETH NAGLE
Green Building Rough 4/20/2021 Approved KENNETH NAGLE
HVAC-Final 4/20/2021 Approved KENNETH NAGLE
MERV13>=Final 4/20/2021 Approved KENNETH NAGLE
MERV13>=Rough 4/20/2021 Approved KENNETH NAGLE
PLUMBING-Final 4/20/2021 Not Ready for Inspection KENNETH NAGLE
SGSOV-Seismic Gas S/O Valve 4/20/2021 SGSOV Approved KENNETH NAGLE
Smoke Detectors 4/20/2021 Not Ready for Inspection KENNETH NAGLE
Final 4/28/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 4/28/2021 Approved OGANES TARAKHCHYAN
Smoke Detectors 4/28/2021 Approved OGANES TARAKHCHYAN
Verify Rec and Parks Fee Memo 4/30/2021 Approved OGANES TARAKHCHYAN
Final 5/10/2021 OK to Issue CofO OGANES TARAKHCHYAN