1495 W 29TH ST 90007

Certificate Information: 1495 W 29TH ST 90007

Application / Permit
20016-10000-00095
Plan Check / Job No.
B20LA00071
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(5) Apartment
Work Description
EPLAN 1648 - Soft-Story seismic retrofit per LABC Chapter 93: USING (3) SPECIAL CANTILEVERED COLUMNS WITH GRADE BEAMS.
Permit Issued
Issued on 2/10/2021
Issuing Office
Current Status
CofC Issued on 4/27/2021

Permit Application Status History

Submitted 1/8/2020 APPLICANT
Assigned to Plan Check Engineer 1/29/2020 DANIEL YIP
Corrections Issued 2/4/2020 DANIEL YIP
Quality Review Completed 2/12/2020 HANS SANTIAGO
Applicant returned to address corrections 4/14/2020 DANIEL YIP
Plan Check Approved 5/8/2020 DANIEL YIP
Issued 2/10/2021 APPLICANT
OK for CofC 4/21/2021 DARRYL ARNOLD
CofC Issued 4/27/2021 ERNESTO CORRAL

Permit Application Clearance Information

HPOZ Cleared 4/23/2020 LYDIA CHAPMAN
Tenant Habitability Plan Cleared 2/8/2021 MICHAEL SOTO

Contact Information

Contractor Retrofitting360 Inc; Lic. No.: 1039226-B 19562 VENTURA BLVD# 230      TARZANA, CA 91356
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 743 S SIERRA VISTA AVE C      ALHAMBRA, CA 91801

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Steel/Welding 3/1/2021 Conditional Approval MARK FERRARI
Pre-Inspection 3/2/2021 Approved DARRYL ARNOLD
Footing/Foundation/Slab 3/16/2021 Approved DARRYL ARNOLD
Interior/Exterior Lathing 4/8/2021 Conditional Approval DARRYL ARNOLD
Reinforced Concrete Frame 4/8/2021 Approved DARRYL ARNOLD
Structural Steel Frame 4/8/2021 Approved DARRYL ARNOLD
Wood Frame 4/8/2021 Approved DARRYL ARNOLD
Interior/Exterior Lathing 4/9/2021 Conditional Approval DARRYL ARNOLD
Final 4/21/2021 OK for CofC DARRYL ARNOLD
METHANE-Final 4/21/2021 Approved DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 4/21/2021 SGSOV Approved DARRYL ARNOLD
Smoke Detectors 4/21/2021 Approved DARRYL ARNOLD