1215 W 36TH ST 90007

Certificate Information: 1215 W 36TH ST 90007

Application / Permit
20016-10000-00093
Plan Check / Job No.
B20LA00069
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Soft-Story seismic retrofit per LABC Chapter 93: add one steel moment frame
Permit Issued
Issued on 7/7/2020
Issuing Office
Current Status
CofC Issued on 1/12/2022

Permit Application Status History

Submitted 1/15/2020 APPLICANT
Assigned to Plan Check Engineer 1/22/2020 DANIEL SANJUAN
Corrections Issued 1/31/2020 DANIEL SANJUAN
Quality Review Completed 2/6/2020 HANS SANTIAGO
Plan Check Approved 5/28/2020 DANIEL SANJUAN
Issued 7/7/2020 APPLICANT
OK for CofC 9/21/2021 DARRYL ARNOLD
CofC Issued 1/12/2022 NICK LAROCCA

Permit Application Clearance Information

Tenant Habitability Plan Cleared 6/23/2020 MICHAEL SOTO
Miscellaneous Cleared 7/7/2020 ADRIAN HERNANDEZ

Contact Information

Engineer Gorgy,, Moheb Shohdy; Lic. No.: NA53260       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/13/2020 Approved DARRYL ARNOLD
Excavation/Setback/Form/Re-Bar 8/4/2020 Corrections Issued JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 8/12/2020 Approved JOEY BUCHANAN
Wood Frame 8/18/2020 Conditional Approval JOEY BUCHANAN
Interior/Exterior Lathing 9/2/2020 Approved JOEY BUCHANAN
Interior/Exterior Lathing 9/3/2020 Approved JOEY BUCHANAN
Final 2/8/2021 Corrections Issued RUSSELL BONVOULOIR
METHANE-Final 2/8/2021 Approved RUSSELL BONVOULOIR
SGSOV-Seismic Gas S/O Valve 2/8/2021 SGSOV Not Ready RUSSELL BONVOULOIR
Smoke Detectors 2/8/2021 Approved RUSSELL BONVOULOIR
Final 8/4/2021 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 8/4/2021 SGSOV Not Ready DARRYL ARNOLD
Final 9/21/2021 OK for CofC DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 9/21/2021 SGSOV Approved DARRYL ARNOLD