1228 N VIRGIL AVE 90029
Certificate Information: 1228 N VIRGIL AVE 90029
- Application / Permit
- 20016-10000-00020
- Plan Check / Job No.
- B20LA00022
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CHAPTER 93 INSTALL 1 (N) SCCS AND WOOD SHEAR WALL
- Permit Issued
- Issued on 12/16/2022
- Issuing Office
- Current Status
- CofC Issued on 9/18/2023
Permit Application Status History
| Submitted | 1/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/22/2020 | JESSE VIDUYA |
| Corrections Issued | 1/27/2020 | JESSE VIDUYA |
| Quality Review Completed | 1/30/2020 | HANS SANTIAGO |
| Building Plans Picked Up | 2/10/2020 | APPLICANT |
| Applicant returned to address corrections | 2/24/2021 | JESSE VIDUYA |
| Applicant returned to address corrections | 5/24/2021 | JESSE VIDUYA |
| Plan Check Approved | 7/19/2021 | JESSE VIDUYA |
| Issued | 12/16/2022 | APPLICANT |
| OK for CofC | 9/18/2023 | VAHE KELEDJIAN |
| CofC Issued | 9/18/2023 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 12/12/2022 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Alpha Structural Inc; Lic. No.: 663409-B | 8334 FOOTHILL BLVD SUNLAND, CA 91040 |
| Engineer | Zelada,, Mynor Anibal; Lic. No.: C48666 | 14545 VICTORY BLVD 405 VAN NUYS, CA 91411 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/5/2023 | Corrections Issued | VAHE KELEDJIAN |
| Deputy Drilled-In Anchors | 6/6/2023 | Conditional Approval | VAHE KELEDJIAN |
| Wood Frame | 6/13/2023 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 6/27/2023 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 7/14/2023 | Conditional Approval | DARRYL ARNOLD |
| Final | 8/3/2023 | Corrections Issued | VAHE KELEDJIAN |
| SGSOV-Seismic Gas S/O Valve | 8/3/2023 | SGSOV Approved | VAHE KELEDJIAN |
| Smoke Detectors | 8/3/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
| Final | 8/4/2023 | Partial Inspection | VAHE KELEDJIAN |
| Smoke Detectors | 8/4/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
| Final | 9/15/2023 | No Access for Inspection | MARTIN TAVITIAN |
| Smoke Detectors | 9/15/2023 | No Access for Inspection | MARTIN TAVITIAN |
| Final | 9/18/2023 | OK for CofC | VAHE KELEDJIAN |
| Smoke Detectors | 9/18/2023 | Approved | VAHE KELEDJIAN |