1331 W 84TH ST 90044
Certificate Information: 1331 W 84TH ST 90044
- Application / Permit
- 20014-70000-01124
- Plan Check / Job No.
- B20SL00406
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 1 STORY ADDITION (12.5' x 17.5') AT FRONT OF EXISTING 1 STORY SINGLE FAMILY DEWLLING WITH ATTACHED CARPORT (NFPA 13D THUR OUT)
- Permit Issued
- Issued on 4/29/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | AUNG SOE |
| Corrections Issued | 3/23/2020 | AUNG SOE |
| Quality Review Completed | 3/27/2020 | ALLEN MANALANSAN |
| Building Plans Picked Up | 4/28/2020 | APPLICANT |
| Applicant returned to address corrections | 9/8/2020 | AUNG SOE |
| Green Plans Picked Up | 9/21/2020 | APPLICANT |
| Applicant returned to address corrections | 12/22/2020 | AUNG SOE |
| Applicant returned to address corrections | 11/5/2021 | AUNG SOE |
| Applicant returned to address corrections | 2/2/2022 | AUNG SOE |
| Plan Check Approved | 4/6/2022 | AUNG SOE |
| Plan Check Approved | 4/26/2022 | AUNG SOE |
| Issued | 4/29/2022 | APPLICANT |
| CofO in Progress | 1/13/2023 | MICHAEL LEWIS |
| No Progress | 1/13/2023 | SCOTT FINNILA |
| CofO in Progress | 1/13/2023 | SCOTT FINNILA |
| CofO in Progress | 3/6/2023 | MICHAEL LEWIS |
| Permit Finaled | 3/11/2023 | DEROLD HAUFF |
| CofO Issued | 3/11/2023 | DEROLD HAUFF |
| Permit Finaled | 3/11/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/29/2020 | CECILIO NAVARRO |
| ZI | Cleared | 10/27/2021 | TERRI OSBORNE |
| Roof/Waste drainage to street | Cleared | 11/9/2021 | JEANETTE VONG |
| Sewer availability | Cleared | 11/16/2021 | PAMELA TENEZA |
| Tenant Habitability Plan | Cleared | 12/21/2021 | PHILLIP MUNGUIA |
| Green Code | Cleared | 1/24/2022 | DONALD CRICHLOW |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2022 | PAMELA TENEZA |
| Hydrant and Access approval | Cleared | 3/29/2022 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/27/2022 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 6/27/2022 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 7/26/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 8/18/2022 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 8/25/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 8/25/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 9/1/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 9/1/2022 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 9/12/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 9/12/2022 | Approved | LILIANA PORTILLO |
| Green Building Rough | 9/12/2022 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 9/12/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 9/12/2022 | Approved | LILIANA PORTILLO |
| Insulation | 9/23/2022 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 10/14/2022 | Approved | LILIANA PORTILLO |
| Final | 10/31/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Final | 10/31/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 10/31/2022 | SGSOV Not Ready | LILIANA PORTILLO |
| Smoke Detectors | 10/31/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 1/4/2023 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 1/4/2023 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 1/4/2023 | SGSOV Not Ready | MICHAEL LEWIS |
| Smoke Detectors | 1/4/2023 | Approved | MICHAEL LEWIS |
| Final | 1/12/2023 | Not Ready for Inspection | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 1/12/2023 | SGSOV Approved | MICHAEL LEWIS |
| Final | 1/17/2023 | Corrections Issued | MICHAEL LEWIS |
| Final | 3/6/2023 | OK to Issue CofO | MICHAEL LEWIS |