5139 S BRYNHURST AVE 90043

Certificate Information: 5139 S BRYNHURST AVE 90043

Application / Permit
20014-70000-00815
Plan Check / Job No.
B20SL00303
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2ND STORY ADDITION TO (E) GARAGE FOR ACCESSORY DWELLING UNIT PER ORDINANCE.
Permit Issued
Issued on 1/27/2022
Issuing Office
Current Status
CofO Issued on 5/22/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/24/2020 APPLICANT
Assigned to Plan Check Engineer 3/20/2020 FARSHAD ALIMOHAMADI
Corrections Issued 3/24/2020 FARSHAD ALIMOHAMADI
Quality Review Completed 3/25/2020 STANLEY RAAP
Green Plans Picked Up 4/20/2020 APPLICANT
Applicant returned to address corrections 9/14/2021 FARSHAD ALIMOHAMADI
Plan Check Approved 12/2/2021 FARSHAD ALIMOHAMADI
Issued 1/27/2022 APPLICANT
Building Plans Picked Up 4/7/2022 APPLICANT
CofO in Progress 5/20/2026 LUIS CASTRO
CofO Issued 5/22/2026 DEROLD HAUFF
Permit Finaled 5/22/2026 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 4/16/2020 VIVIAN LAO
Address approval Cleared 5/13/2020 EMIL KYUPELYAN
Construction near power lines Cleared 10/19/2020 RIDWAN HARDY
Sewer availability Cleared 7/1/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 7/8/2021 CELINA MORENO
Low Impact Development Cleared 8/16/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 8/19/2021 NAZILA NOORIFAR

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/2/2023 No Access for Inspection ANTHONY EGSON
Gas Test 6/5/2023 Approved ANTHONY EGSON
Sewer 6/5/2023 Approved ANTHONY EGSON
ELECTRICAL-Rough 6/27/2024 No Access for Inspection MICHAEL LEWIS
PLUMBING-Rough 6/27/2024 No Access for Inspection MICHAEL LEWIS
ELECTRICAL-Rough 10/2/2024 Approved ANTHONY EGSON
HVAC-Rough 12/12/2024 Corrections Issued BARRY HACHE
PLUMBING-Rough 12/12/2024 Corrections Issued BARRY HACHE
HVAC-Rough 12/19/2024 Approved LUIS CASTRO
PLUMBING-Rough 12/19/2024 Approved LUIS CASTRO
BUILDING-Rough-Frame 1/13/2025 Corrections Issued LUIS CASTRO
Green Building Rough 1/13/2025 Approved LUIS CASTRO
Insulation 1/30/2025 Corrections Issued LUIS CASTRO
Insulation 2/4/2025 Partial Approval LUIS CASTRO
Drywall Nailing 3/12/2025 Approved LUIS CASTRO
Shower Pan 3/12/2025 Approved LUIS CASTRO
Special/Order Compliance 1/14/2026 Corrections Issued LUIS CASTRO
Underground Mechanical 1/14/2026 Partial Approval LUIS CASTRO
ELECTRICAL-Rough 1/20/2026 Not Ready for Inspection LUIS CASTRO
ELECTRICAL-Final 1/29/2026 Not Ready for Inspection LUIS CASTRO
ELECTRICAL-Rough 2/13/2026 Not Ready for Inspection LUIS CASTRO
BUILDING-Rough-Frame 3/27/2026 Approved LUIS CASTRO
Final 3/27/2026 Corrections Issued LUIS CASTRO
Footing/Foundation/Slab 3/27/2026 Approved LUIS CASTRO
Green Building Final 3/27/2026 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 3/27/2026 SGSOV Not Ready LUIS CASTRO
Smoke Detectors 3/27/2026 Corrections Issued LUIS CASTRO
ELECTRICAL-Final 4/7/2026 Approved LUIS CASTRO
Final 4/7/2026 Conditional Approval LUIS CASTRO
HVAC-Final 4/7/2026 Approved LUIS CASTRO
PLUMBING-Final 4/7/2026 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 4/7/2026 SGSOV Approved LUIS CASTRO
Smoke Detectors 4/7/2026 Approved LUIS CASTRO
Final 5/20/2026 OK to Issue CofO LUIS CASTRO