3914 W 58TH PL 90043
Certificate Information: 3914 W 58TH PL 90043
- Application / Permit
- 20014-70000-00565
- Plan Check / Job No.
- B20SL00222
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF 308SF AT THE REAR OF (E) SFD. ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 3/2/2020
- Issuing Office
- South Los Angeles
- Current Status
- Issued on 3/2/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/7/2020 | LUKE GONZALES |
| Corrections Issued | 2/7/2020 | LUKE GONZALES |
| Plan Check Approved | 3/2/2020 | RICARDO RAMIREZ |
| Issued | 3/2/2020 | LADBS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/13/2020 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 2/13/2020 | KIRK LINKLATER |
| Roof/Waste drainage to street | Cleared | 2/13/2020 | JEANIE LAM |
| Sewer availability | Cleared | 2/13/2020 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/3/2020 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 3/5/2020 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 3/9/2020 | Approved | HORACE FULTZ |
| ELECTRICAL-Rough | 3/9/2020 | Approved | HORACE FULTZ |
| Green Building Rough | 3/9/2020 | Approved | HORACE FULTZ |
| PLUMBING-Rough | 3/9/2020 | Approved | HORACE FULTZ |
| Drywall Nailing | 3/10/2020 | Approved | FREDDIE RIVERA |
| Insulation | 3/10/2020 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 3/10/2020 | Partial Approval | FREDDIE RIVERA |
| Final | 3/23/2020 | Not Ready for Inspection | HORACE FULTZ |
| Green Building Final | 3/23/2020 | Approved | HORACE FULTZ |
| SGSOV-Seismic Gas S/O Valve | 3/23/2020 | SGSOV Not Ready | HORACE FULTZ |
| Smoke Detectors | 3/23/2020 | Not Ready for Inspection | HORACE FULTZ |
| ELECTRICAL-Final | 3/27/2020 | Approved | ALEJANDRO DE ARTOLA |
| Final | 3/27/2020 | Conditional Approval | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/27/2020 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 3/27/2020 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 3/27/2020 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 3/27/2020 | Approved | ALEJANDRO DE ARTOLA |