3840 W 59TH ST 90043
Certificate Information: 3840 W 59TH ST 90043
- Application / Permit
- 20014-70000-00275
- Plan Check / Job No.
- B20SL00110
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 12'X18' GARAGE TO ACCESSORY DWELLING UNIT AND ADD 26'X21'6" GROUND FLOOR ADDITION TO THE EXITING GARAGE STRUCTURE
- Permit Issued
- Issued on 12/23/2020
- Issuing Office
- Current Status
- CofO Issued on 10/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/5/2020 | AMIR DANAI |
| Corrections Issued | 2/7/2020 | AMIR DANAI |
| Quality Review Completed | 2/28/2020 | TIEN JEN WANG |
| Building Plans Picked Up | 3/4/2020 | APPLICANT |
| Green Plans Picked Up | 8/14/2020 | APPLICANT |
| Plan Check Approved | 12/8/2020 | AMIR DANAI |
| Issued | 12/23/2020 | APPLICANT |
| CofO in Progress | 9/29/2021 | FREDDIE RIVERA |
| CofO Issued | 10/2/2021 | DEROLD HAUFF |
| Permit Finaled | 10/2/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/23/2020 | JEANIE LAM |
| ZI | Cleared | 7/23/2020 | RUBEN VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/5/2020 | JEANIE LAM |
| Sewer availability | Cleared | 8/5/2020 | JEANIE LAM |
| Green Code | Cleared | 8/13/2020 | KHEDER ALRAZAA |
| Low Impact Development | Cleared | 10/15/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 10/20/2020 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/16/2021 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 2/23/2021 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 4/6/2021 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2021 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 4/6/2021 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 4/21/2021 | Approved | DAVID FEILER |
| ELECTRICAL-Rough | 4/21/2021 | Not Ready for Inspection | DAVID FEILER |
| Green Building Rough | 4/21/2021 | Approved | DAVID FEILER |
| HVAC-Rough | 4/21/2021 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 4/21/2021 | Partial Approval | DAVID FEILER |
| PLUMBING-Rough | 4/21/2021 | Approved | DAVID FEILER |
| Shower Pan | 4/21/2021 | Not Ready for Inspection | DAVID FEILER |
| Wood Frame | 4/21/2021 | Approved | DAVID FEILER |
| Insulation | 5/3/2021 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 5/3/2021 | Approved | FREDDIE RIVERA |
| Shower Pan | 5/3/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Drywall Nailing | 5/10/2021 | Partial Approval | SABAS ALONSO |
| Shower Pan | 5/10/2021 | Approved | SABAS ALONSO |
| Drywall Nailing | 5/14/2021 | Approved | SABAS ALONSO |
| Shower Pan | 5/17/2021 | Approved | SABAS ALONSO |
| Sewer | 6/15/2021 | Approved | DAVID FEILER |
| Underground Mechanical | 6/15/2021 | Approved | DAVID FEILER |
| Final | 8/27/2021 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 8/27/2021 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 8/27/2021 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 8/27/2021 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 9/23/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Final | 9/23/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 9/23/2021 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 9/23/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Final | 9/28/2021 | OK to Issue CofO | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 9/28/2021 | SGSOV Approved | FREDDIE RIVERA |