1899 N LUCRETIA AVE 90026

Certificate Information: 1899 N LUCRETIA AVE 90026

Application / Permit
20014-70000-00190
Plan Check / Job No.
B20SL00082
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
36' X 39'-11" IRREGULAR SHAPED 2-STORY MAJOR ADDITION W/ ATTACHED PORCH & REMODEL TO CONVERT (E) CRAWLSPACE TO A UNIT TO CREATE A (N) DUPLEX. NFPA 13 D FIRE SPRINKLERS REQ'D THROUGHOUT
Permit Issued
Issued on 2/17/2023
Issuing Office
Valley
Current Status
CofO Issued on 1/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/16/2020 APPLICANT
Assigned to Plan Check Engineer 2/27/2020 MARVEL DELACRUZ
Corrections Issued 3/3/2020 MARVEL DELACRUZ
Quality Review Completed 3/4/2020 GUANG MIN TUNG
Building Plans Picked Up 3/10/2020 APPLICANT
Green Plans Picked Up 3/10/2020 APPLICANT
Applicant returned to address corrections 7/25/2022 RAPHAEL ROSAS
Applicant returned to address corrections 1/26/2023 RAPHAEL ROSAS
Applicant returned to address corrections 2/1/2023 RAPHAEL ROSAS
Plan Check Approved 2/17/2023 RAPHAEL ROSAS
Issued 2/17/2023 APPLICANT
CofO in Progress 7/26/2024 HAMIK HARTOUNIAN
Permit Finaled 1/9/2025 DEROLD HAUFF
CofO Issued 1/9/2025 DEROLD HAUFF
Permit Finaled 1/9/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/15/2022 CHRISTOPHER ROCHA
BHO/Hillside ordinance Cleared 7/15/2022 CHRISTOPHER ROCHA
BHO/Hillside ordinance Cleared 7/15/2022 CHRISTOPHER ROCHA
BHO/Hillside ordinance Cleared 7/15/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 7/15/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 7/20/2022 CHRISTOPHER ROCHA
BHO/Hillside ordinance Cleared 10/13/2022 CHRISTOPHER ROCHA
BHO/Hillside ordinance Cleared 10/13/2022 CHRISTOPHER ROCHA
Distance to fire station Cleared 10/17/2022 LAVEON RIDER
Tenant Habitability Plan Cleared 12/21/2022 RICARDO BOHORQUEZ
Low Impact Development Cleared 12/22/2022 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 12/22/2022 CHRISTOPHER ROCHA
Green Code Cleared 2/1/2023 MARVEL DELACRUZ
Hydrant and Access approval Cleared 2/6/2023 LAVEON RIDER
GPI Written Notices Cleared 2/17/2023 MARVEL DELACRUZ
Grading Pre-Inspection Cleared 2/17/2023 MARVEL DELACRUZ

Contact Information

Contractor Owner-Builder       ,
Engineer Guo,, Dongfan; Lic. No.: C92889 668 N ATLANTIC BLVD UNIT B      ALHAMBRA, CA 91801
Engineer Mercado,, Lizandro; Lic. No.: S4331 27240 TURNBERRY LN STE 200      VALENCIA, CA 91355
Geologist Tsao,, Tze-Tzong; Lic. No.: EG1783 9428 ETON AVENUE #M      CHATSWORTH, CA 91311

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 4/12/2023 Partial Approval THOMAS LOGRASSO
Deputy Reinf. Concrete 4/13/2023 Conditional Approval THOMAS LOGRASSO
Deputy Drilled-In Anchors 4/24/2023 Conditional Approval THOMAS LOGRASSO
Deputy Reinf. Concrete 4/24/2023 Conditional Approval THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 4/25/2023 Partial Approval THOMAS LOGRASSO
Footing/Foundation/Slab 4/25/2023 Not Ready for Inspection THOMAS LOGRASSO
Deputy Reinf. Concrete 4/26/2023 Approved FREDDIE RIVERA
Footing/Foundation/Slab 5/24/2023 Approved THOMAS LOGRASSO
Deputy Steel/Welding 6/22/2023 Approved DONALD CRICHLOW
Structural Steel Frame 7/3/2023 Corrections Issued THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 7/27/2023 Partial Approval THOMAS LOGRASSO
Deputy Wood Construction 8/29/2023 Conditional Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 11/14/2023 Corrections Issued THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 11/14/2023 Corrections Issued THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 11/22/2023 Partial Approval JOAQUIN GREENOUGH
Wood Frame 11/22/2023 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 11/29/2023 Corrections Issued THOMAS LOGRASSO
Green Building Rough 11/29/2023 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Rough 11/29/2023 Partial Approval THOMAS LOGRASSO
PLUMBING-Rough 11/29/2023 Partial Approval THOMAS LOGRASSO
Deputy Wood Construction 12/1/2023 Conditional Approval THOMAS LOGRASSO
Insulation 12/19/2023 Partial Approval THOMAS LOGRASSO
Interior/Exterior Lathing 12/19/2023 Partial Approval THOMAS LOGRASSO
Drywall Nailing 1/5/2024 Partial Approval THOMAS LOGRASSO
ELECTRICAL-Rough 1/22/2024 Approved THOMAS LOGRASSO
PLUMBING-Rough 1/22/2024 Approved THOMAS LOGRASSO
Shower Pan 1/22/2024 Partial Approval THOMAS LOGRASSO
HVAC-Rough 2/6/2024 Not Ready for Inspection THOMAS LOGRASSO
Insulation 2/12/2024 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Rough 2/15/2024 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 2/21/2024 Approved THOMAS LOGRASSO
Drywall Nailing 2/21/2024 Approved THOMAS LOGRASSO
Green Building Rough 2/21/2024 Approved THOMAS LOGRASSO
HVAC-Rough 2/21/2024 Approved THOMAS LOGRASSO
Final 4/16/2024 Not Ready for Inspection THOMAS LOGRASSO
Green Building Final 4/16/2024 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 4/16/2024 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 4/16/2024 Approved THOMAS LOGRASSO
Final 7/19/2024 OK to Issue CofO HAMIK HARTOUNIAN
Green Building Final 7/19/2024 Approved HAMIK HARTOUNIAN