9613 S BANDERA ST 90002

Certificate Information: 9613 S BANDERA ST 90002

Application / Permit
20014-70000-00169
Plan Check / Job No.
B20SL00074
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
1-STORY 18.5' X 14.167' ADU ADDITION TO EXISTING 18.5' X 11.33' GARAGE TO BE CONVERTED TO ADU PER WFPP. "COMPLY WITH DEPARTMENT ORDER effective date 12/27/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 11/19/2020
Issuing Office
Current Status
CofO in Progress on 9/9/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/15/2020 APPLICANT
Assigned to Plan Check Engineer 2/7/2020 CRYSTEL MAALOUF
Corrections Issued 2/14/2020 CRYSTEL MAALOUF
Quality Review Completed 2/21/2020 BILL STUTSMAN
Building Plans Picked Up 2/27/2020 APPLICANT
Applicant returned to address corrections 5/21/2020 CRYSTEL MAALOUF
Applicant returned to address corrections 7/15/2020 CRYSTEL MAALOUF
Green Plans Picked Up 7/20/2020 APPLICANT
Applicant returned to address corrections 11/6/2020 CRYSTEL MAALOUF
Plan Check Approved 11/18/2020 CRYSTEL MAALOUF
Issued 11/19/2020 APPLICANT
CofO in Progress 9/9/2024 KEITH EDGHILL

Permit Application Clearance Information

Address approval Cleared 3/16/2020 ELENA LOPEZ
Eng Process Fee Ord 176,300 Cleared 3/16/2020 ELENA LOPEZ
Roof/Waste drainage to street Cleared 3/16/2020 ELENA LOPEZ
Green Code Cleared 5/22/2020 VIVIAN LAO
Sewer availability Cleared 6/12/2020 RENZ SORIANO
Stormwater Pollution Mitigatn Cleared 10/26/2020 MARTIN FRAGOSO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KELLY WARNER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
PAUL BECKER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
KEITH EDGHILL, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GONZALEZ, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/26/2021 Partial Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 3/16/2021 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 3/16/2021 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 3/16/2021 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 3/16/2021 Not Ready for Inspection EUGENE CASSIDY
Insulation 3/16/2021 Not Ready for Inspection EUGENE CASSIDY
Interior/Exterior Lathing 3/16/2021 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 3/16/2021 Not Ready for Inspection EUGENE CASSIDY
Pre-Inspection 3/16/2021 Not Ready for Inspection EUGENE CASSIDY
Wood Frame 3/16/2021 Not Ready for Inspection EUGENE CASSIDY
Pre-Inspection 8/10/2023 Corrections Issued JOHN KLARIN
BUILDING-Rough-Frame 9/1/2023 Partial Approval JOHN KLARIN
Green Building Rough 9/1/2023 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 9/1/2023 Corrections Issued JOHN KLARIN
PLUMBING-Final 10/6/2023 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Rough 10/13/2023 Approved JOHN KLARIN
PLUMBING-Rough 10/13/2023 Approved JOHN KLARIN
BUILDING-Rough-Frame 10/24/2023 Approved JAMES CHAVEZ
Final 10/24/2023 Corrections Issued JAMES CHAVEZ
Footing/Foundation/Slab 10/24/2023 Approved JAMES CHAVEZ
Green Building Final 10/24/2023 Not Ready for Inspection JAMES CHAVEZ
Green Building Rough 10/24/2023 Approved JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 10/24/2023 SGSOV Not Ready JAMES CHAVEZ
Smoke Detectors 10/24/2023 Approved JAMES CHAVEZ
ELECTRICAL-Final 11/2/2023 Approved JOHN KLARIN
Final 1/9/2024 Corrections Issued JOHN KLARIN
Green Building Final 1/9/2024 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 1/9/2024 SGSOV Approved JOHN KLARIN
Final 4/11/2024 Conditional Approval BEN MOLSTAD
Service/Power Release 4/11/2024 Not Ready for Inspection BEN MOLSTAD
Final 4/12/2024 Corrections Issued BEN MOLSTAD
Final 4/24/2024 Corrections Issued BEN MOLSTAD
Final 5/9/2024 Corrections Issued ANSON MAGLASANG
Final 6/28/2024 Partial Approval BEN MOLSTAD
ELECTRICAL-Final 7/29/2024 Not Ready for Inspection BEN MOLSTAD
Final 7/29/2024 Corrections Issued BEN MOLSTAD
Final 8/12/2024 Not Ready for Inspection KEITH EDGHILL
Final 9/9/2024 OK to Issue CofO KEITH EDGHILL