8017 N ENCINO AVE 91325
Certificate Information: 8017 N ENCINO AVE 91325
- Application / Permit
- 20014-70000-00154
- Plan Check / Job No.
- B20SL00063
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 808 SF (37.25'x22.67') ADU PER WFPP
- Permit Issued
- Issued on 3/11/2022
- Issuing Office
- Current Status
- CofO Issued on 4/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/7/2020 | STARR CHEN |
| Corrections Issued | 2/12/2020 | STARR CHEN |
| Quality Review Completed | 2/13/2020 | LAWRENCE QUIRANTE |
| Green Plans Picked Up | 2/14/2020 | APPLICANT |
| Building Plans Picked Up | 2/21/2020 | APPLICANT |
| Plan Check Approved | 3/19/2020 | STARR CHEN |
| Issued | 3/11/2022 | APPLICANT |
| CofO in Progress | 3/6/2023 | RAUL OLAGI |
| No Progress | 3/16/2023 | ROBERT GOLD |
| CofO in Progress | 4/12/2023 | MICHAEL SMITH |
| CofO Issued | 4/12/2023 | MICHAEL SMITH |
| Permit Finaled | 4/12/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 2/27/2020 | ERNEST FRESQUEZ |
| Address approval | Cleared | 2/28/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 3/17/2020 | ELENA LOPEZ |
| Green Code | Cleared | 3/17/2020 | COLIN LOREDO |
| Hydrant and Access approval | Cleared | 3/17/2020 | GEORGE SUCHAND |
| Sewer availability | Cleared | 3/17/2020 | ELENA LOPEZ |
| Low Impact Development | Cleared | 3/19/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 3/19/2020 | RENZ SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/18/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 4/27/2022 | Corrections Issued | DEANDRE HOFFMAN |
| PLUMBING-Rough | 4/29/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 5/9/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 5/9/2022 | Corrections Issued | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 5/13/2022 | Not Ready for Inspection | RAUL OLAGI |
| Footing/Foundation/Slab | 5/13/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 5/13/2022 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 5/18/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 5/18/2022 | Partial Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2022 | Partial Approval | DEANDRE HOFFMAN |
| Wood Frame | 7/18/2022 | Corrections Issued | DEANDRE HOFFMAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2022 | Partial Approval | ALAN MORELOS |
| PLUMBING-Rough | 8/4/2022 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 8/9/2022 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 8/9/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 8/17/2022 | Not Ready for Inspection | RAUL OLAGI |
| BUILDING-Rough-Frame | 8/23/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Rough | 8/23/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 8/23/2022 | Corrections Issued | RAUL OLAGI |
| Interior/Exterior Lathing | 8/23/2022 | Partial Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 8/26/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 8/26/2022 | Approved | RAUL OLAGI |
| Insulation | 8/26/2022 | Approved | RAUL OLAGI |
| Sewer | 8/26/2022 | Not Ready for Inspection | RAUL OLAGI |
| Drywall Nailing | 9/6/2022 | Approved | RAUL OLAGI |
| Sewer | 9/6/2022 | Approved | RAUL OLAGI |
| Underground Mechanical | 9/6/2022 | Approved | RAUL OLAGI |
| Underground Mechanical | 11/2/2022 | Corrections Issued | RAUL OLAGI |
| Gas Test | 11/14/2022 | Approved | RAUL OLAGI |
| Underground Mechanical | 11/14/2022 | Approved | RAUL OLAGI |
| PLUMBING-Final | 12/2/2022 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Final | 1/18/2023 | Corrections Issued | RAUL OLAGI |
| Final | 1/18/2023 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 1/18/2023 | Approved | RAUL OLAGI |
| HVAC-Final | 1/18/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 1/18/2023 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 1/18/2023 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 1/18/2023 | Approved | RAUL OLAGI |
| Final | 3/6/2023 | OK to Issue CofO | RAUL OLAGI |