1616-1618 W 259TH PL 90710

Certificate Information: 1616-1618 W 259TH PL 90710

Application / Permit
20014-40000-01311
Plan Check / Job No.
B20SP00306
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Ground floor addition to (E) duplex with attached garage. All work per engineered design.
Permit Issued
Issued on 12/9/2020
Issuing Office
Current Status
CofO Issued on 9/30/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/19/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 JASON JANGADA
Corrections Issued 3/19/2020 JASON JANGADA
Issued 12/9/2020 APPLICANT
CofO in Progress 9/21/2021 JOHN KLARIN
Permit Finaled 9/30/2021 DEROLD HAUFF
CofO Issued 9/30/2021 DEROLD HAUFF
Permit Finaled 9/30/2021 DEROLD HAUFF

Permit Application Clearance Information

Tenant Habitability Plan Cleared 3/26/2020 PHILLIP MUNGUIA
Roof/Waste drainage to street Cleared 4/1/2020 EMIL KYUPELYAN
Sewer availability Cleared 4/1/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 4/20/2020 JAMES KHO

Contact Information

Contractor Owner-Builder       ,
Engineer Hale,, Ronald Richard; Lic. No.: C17056 1869 PALACIOS DR      SAN PEDRO, CA 90732

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/3/2021 Approved JOHN KLARIN
Footing/Foundation/Slab 3/11/2021 Approved JOHN KLARIN
BUILDING-Rough-Frame 4/12/2021 Corrections Issued JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 4/12/2021 Partial Approval JOHN KLARIN
ELECTRICAL-Rough 4/19/2021 Approved JOHN KLARIN
Wood Frame 4/19/2021 Approved JOHN KLARIN
Insulation 4/26/2021 No Access for Inspection SABAS ALONSO
Insulation 4/29/2021 Approved SABAS ALONSO
Drywall Nailing 5/11/2021 Approved SABAS ALONSO
Interior/Exterior Lathing 5/11/2021 Approved SABAS ALONSO
BUILDING-Rough-Frame 8/5/2021 Approved JOHN KLARIN
Final 8/5/2021 Corrections Issued JOHN KLARIN
Green Building Final 8/5/2021 Approved JOHN KLARIN
Green Building Rough 8/5/2021 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 8/5/2021 SGSOV Approved JOHN KLARIN
Smoke Detectors 8/5/2021 Approved JOHN KLARIN
ELECTRICAL-Final 9/20/2021 Approved JOHN KLARIN
Final 9/20/2021 OK to Issue CofO JOHN KLARIN
HVAC-Final 9/20/2021 Approved JOHN KLARIN
PLUMBING-Final 9/20/2021 Approved JOHN KLARIN