10519 W TROON AVE 90064

Certificate Information: 10519 W TROON AVE 90064

Application / Permit
20014-40000-01273
Plan Check / Job No.
B20SP00293
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1-story addition (414 sf) to rear side of (e) single story SFD (1,107 sf) to add a bedroom and a bathroom (total = 1,521 sf)
Permit Issued
Issued on 8/19/2021
Issuing Office
Current Status
CofO Issued on 2/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/17/2020 APPLICANT
Assigned to Plan Check Engineer 4/8/2020 REZA HAGHIGHAT
Green Plans Picked Up 4/15/2020 APPLICANT
Corrections Issued 4/16/2020 REZA HAGHIGHAT
Quality Review Completed 4/24/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 6/26/2020 APPLICANT
Applicant returned to address corrections 5/14/2021 REZA HAGHIGHAT
Applicant returned to address corrections 6/3/2021 REZA HAGHIGHAT
Plan Check Approved 7/15/2021 REZA HAGHIGHAT
Issued 8/19/2021 APPLICANT
CofO in Progress 1/3/2025 ARAM AVEDISIAN
CofO in Progress 1/3/2025 ARAM AVEDISIAN
CofO in Progress 2/3/2025 BOBBY KEY
CofO Issued 2/7/2025 RICHARD STEINBACH
Permit Finaled 2/7/2025 RICHARD STEINBACH

Permit Application Clearance Information

Low Impact Development Cleared 10/20/2020 MITESH PATEL
Eng Process Fee Ord 176,300 Cleared 1/7/2021 NIKTA MOUSAVI
Roof/Waste drainage to street Cleared 1/13/2021 NIKTA MOUSAVI
Sewer availability Cleared 1/15/2021 NIKTA MOUSAVI
Specific Plan Cleared 2/8/2021 DYLAN SITTIG
GPI Written Notices Cleared 7/15/2021 KAVIAN REFAHI
Grading Pre-Inspection Cleared 7/15/2021 REZA HAGHIGHAT
Green Code Cleared 7/15/2021 RICHARD GARCIA

Contact Information

Contractor Armstrong Cal Builders Inc; Lic. No.: 990992-B 3031 E WILLOW STREET      SIGNAL HILL, CA 90755
Engineer Mani,, Dev; Lic. No.: C62778 P O BOX 1451      DUARTE, CA 91009
Engineer Pukkanasut,, Jirayus; Lic. No.: C73728 15038 CLARK AVE      HACIENDA HEIGHTS, CA 91745
Geologist , ; Lic. No.: GEO2579    1290 N LAKE AVENUE #204    PASADENA, CA 91104

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/27/2021 No Access for Inspection KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 11/2/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Deputy Drilled-In Anchors 4/5/2022 Approved MICHAEL PELHAM
Footing/Foundation/Slab 4/7/2022 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 4/21/2022 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 5/6/2022 Approved KEVIN SARGSYAN
Deputy Drilled-In Anchors 5/16/2022 Conditional Approval KEVIN SARGSYAN
Deputy Drilled-In Anchors 6/22/2022 No Result Entered RONALD WEBER
Wood Frame 7/15/2022 Corrections Issued KEVIN SARGSYAN
Wood Frame 7/20/2022 Corrections Issued OGANES TARAKHCHYAN
BUILDING-Rough-Frame 7/26/2022 Partial Approval STEPHANIE SWANSON
Insulation 7/26/2022 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 7/28/2022 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 1/20/2023 Partial Approval ASHLEY THOMPSON
ELECTRICAL-Rough 1/25/2023 Corrections Issued ASHLEY THOMPSON
PLUMBING-Rough 1/25/2023 Corrections Issued ASHLEY THOMPSON
ELECTRICAL-Rough 1/27/2023 Approved JULIAN AMAYA
HVAC-Rough 1/27/2023 Not Ready for Inspection JULIAN AMAYA
PLUMBING-Rough 1/27/2023 Approved JULIAN AMAYA
HVAC-Rough 2/2/2023 Corrections Issued ASHLEY THOMPSON
HVAC-Rough 3/10/2023 Corrections Issued JOHNNY MIRANDA
Wood Frame 3/10/2023 Corrections Issued JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 3/14/2023 Not Ready for Inspection ASHLEY THOMPSON
HVAC-Rough 3/14/2023 Approved ASHLEY THOMPSON
Special/Order Compliance 3/14/2023 Partial Inspection JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 3/16/2023 Corrections Issued STEPHANIE SWANSON
Deputy Wood Construction 3/20/2023 Conditional Approval ASHLEY THOMPSON
Interior/Exterior Lathing 4/24/2023 Partial Approval CLAYTON GRAHAM
Drywall Nailing 5/30/2023 Approved JOHNNY MIRANDA
Green Building Rough 5/30/2023 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 7/12/2023 Partial Approval CLAYTON GRAHAM
BUILDING-Rough-Frame 6/12/2024 Approved ASHLEY THOMPSON
ELECTRICAL-Final 6/12/2024 Corrections Issued ASHLEY THOMPSON
Final 6/12/2024 Corrections Issued ASHLEY THOMPSON
Green Building Final 6/12/2024 Approved ASHLEY THOMPSON
HVAC-Final 6/12/2024 Corrections Issued ASHLEY THOMPSON
PLUMBING-Final 6/12/2024 Approved ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 6/12/2024 SGSOV Not Required ASHLEY THOMPSON
Service/Power Release 6/12/2024 Not Ready for Inspection ASHLEY THOMPSON
Smoke Detectors 6/12/2024 Approved ASHLEY THOMPSON
Final 7/31/2024 Not Ready for Inspection ASHLEY THOMPSON
Final 9/20/2024 Not Ready for Inspection ASHLEY THOMPSON
Final 12/12/2024 Not Ready for Inspection ARAM AVEDISIAN
Final 1/3/2025 Not Ready for Inspection ARAM AVEDISIAN
Final 2/3/2025 OK to Issue CofO BOBBY KEY