232 E 88TH ST 90003
Certificate Information: 232 E 88TH ST 90003
- Application / Permit
- 20014-40000-00946
- Plan Check / Job No.
- B20SP00223
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **2 of 2** Conversion of and addition to (E) detached accessory buildings (garage and workshop/storage buildings) to create one-story Accessory Dwelling Unit per LAMC 12.22 A.33(c) and (d). All work per engineered design. COMPLY WITH DEPARTMENT ORDER effective date 04/13/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 3/29/2024
- Issuing Office
- Metro
- Current Status
- Issued on 3/29/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/20/2020 | JASON JANGADA |
| Corrections Issued | 3/25/2020 | JASON JANGADA |
| Quality Review Completed | 3/27/2020 | CHRISTOPHER KOMANCHECK |
| Applicant returned to address corrections | 1/25/2021 | JASON JANGADA |
| Green Plans Picked Up | 1/28/2021 | APPLICANT |
| Applicant returned to address corrections | 2/5/2021 | JASON JANGADA |
| Applicant returned to address corrections | 4/19/2021 | JASON JANGADA |
| Applicant returned to address corrections | 7/7/2021 | JASON JANGADA |
| Applicant returned to address corrections | 7/8/2021 | JASON JANGADA |
| Building Plans Picked Up | 7/21/2021 | APPLICANT |
| Applicant returned to address corrections | 3/2/2023 | JASON JANGADA |
| Plan Check Approved | 2/16/2024 | JASON JANGADA |
| Issued | 3/29/2024 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 7/23/2020 | KURT CORRAL |
| Address approval | Cleared | 10/19/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/23/2020 | CECILIO NAVARRO |
| Low Impact Development | Cleared | 1/10/2024 | LUIS LUVANO |
| Green Code | Cleared | 1/19/2024 | DONALD CRICHLOW |
| Roof/Waste drainage to street | Cleared | 2/1/2024 | ERIK BEASLEY |
| Sewer availability | Cleared | 2/9/2024 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Singh,, Jasbir; Lic. No.: C38767 | 16194 EASTRIDGE CT CHINO HILLS, CA 91709 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/18/2024 | Approved | DANIEL GUEVARA |
| Excavation/Setback/Form/Re-Bar | 7/22/2024 | Corrections Issued | DANIEL GUEVARA |
| Rough-Elec/Plmb/HVAC | 12/6/2024 | Approved | DANIEL GONZALEZ |
| Green Building Rough | 1/21/2025 | Approved | DANIEL GUEVARA |
| Interior/Exterior Lathing | 1/21/2025 | Approved | DANIEL GUEVARA |
| BUILDING-Rough-Frame | 3/25/2025 | Approved | DANIEL GUEVARA |
| Drywall Nailing | 3/25/2025 | Approved | DANIEL GUEVARA |
| Final | 3/25/2025 | Not Ready for Inspection | DANIEL GUEVARA |
| Footing/Foundation/Slab | 3/25/2025 | Approved | DANIEL GUEVARA |
| Green Building Final | 3/25/2025 | Not Ready for Inspection | DANIEL GUEVARA |
| HVAC-Final | 3/25/2025 | Approved | DANIEL GUEVARA |
| PLUMBING-Final | 3/25/2025 | Approved | DANIEL GUEVARA |
| SGSOV-Seismic Gas S/O Valve | 3/25/2025 | SGSOV Approved | DANIEL GUEVARA |
| Service/Power Release | 3/25/2025 | Approved | DANIEL GUEVARA |
| Smoke Detectors | 3/25/2025 | Approved | DANIEL GUEVARA |
| ELECTRICAL-Final | 4/15/2025 | Approved | DANIEL GUEVARA |
| Final | 4/15/2025 | Not Ready for Inspection | DANIEL GUEVARA |
| Green Building Final | 4/15/2025 | Not Ready for Inspection | DANIEL GUEVARA |