830 W 64TH ST 90044
Certificate Information: 830 W 64TH ST 90044
- Application / Permit
- 20014-40000-00336
- Plan Check / Job No.
- B20SP00092
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- One-story, irregular-shaped ground floor addition (300 SF) to the rear of (E) one-story Single Family Dwelling to create bedroom, bathroom, and closet. All work per Engineered Design.
- Permit Issued
- Issued on 1/31/2020
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 3/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2020 | CHRISTOPHER KOMANCHECK |
| Corrections Issued | 1/27/2020 | CHRISTOPHER KOMANCHECK |
| Plan Check Approved | 1/28/2020 | CHRISTOPHER KOMANCHECK |
| Issued | 1/31/2020 | LADBS |
| CofO in Progress | 2/9/2022 | ALIZAH MAYAGOITIA |
| Permit Finaled | 3/5/2022 | DEROLD HAUFF |
| CofO Issued | 3/5/2022 | DEROLD HAUFF |
| Permit Finaled | 3/5/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/28/2020 | CHINH DINH |
| Roof/Waste drainage to street | Cleared | 1/28/2020 | CHINH DINH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/5/2020 | Corrections Issued | EUGENE CASSIDY |
| Deputy Drilled-In Anchors | 5/6/2020 | Approved | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 5/8/2020 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 5/20/2020 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 5/20/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 5/26/2020 | Corrections Issued | BRIAN CHRISTIAN |
| BUILDING-Rough-Frame | 6/2/2020 | Partial Approval | BRIAN CHRISTIAN |
| Insulation | 6/9/2020 | Partial Approval | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2020 | Corrections Issued | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2020 | Corrections Issued | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/14/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/26/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 10/26/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 11/2/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 11/2/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 11/10/2020 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 11/10/2020 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 11/10/2020 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 11/10/2020 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 11/23/2020 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 11/23/2020 | Partial Approval | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 9/16/2021 | SGSOV Not Ready | DAVID FEILER |
| ELECTRICAL-Final | 9/20/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 9/20/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 9/20/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 9/20/2021 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 9/20/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 10/15/2021 | Corrections Issued | ADAM ESCOTO |
| Green Building Final | 10/15/2021 | Not Ready for Inspection | ADAM ESCOTO |
| SGSOV-Seismic Gas S/O Valve | 10/15/2021 | SGSOV Approved | ADAM ESCOTO |
| Smoke Detectors | 10/15/2021 | Not Ready for Inspection | ADAM ESCOTO |
| Final | 10/29/2021 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 10/29/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Smoke Detectors | 10/29/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Final | 11/18/2021 | Corrections Issued | HORACE FULTZ |
| Green Building Final | 11/18/2021 | Approved | HORACE FULTZ |
| Smoke Detectors | 11/18/2021 | Approved | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2021 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 12/3/2021 | Corrections Issued | FREDDIE RIVERA |
| Final | 12/15/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Final | 12/21/2021 | Not Ready for Inspection | ADAM ESCOTO |
| Final | 1/12/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Final | 2/4/2022 | Partial Approval | LILIANA PORTILLO |
| ELECTRICAL-Final | 2/9/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 2/9/2022 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| HVAC-Final | 2/9/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 2/9/2022 | Approved | ALIZAH MAYAGOITIA |