720 N SAN PASCUAL AVE 90042

Certificate Information: 720 N SAN PASCUAL AVE 90042

Application / Permit
20014-40000-00140
Plan Check / Job No.
B20SP00043
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition to (E) detached garage to create new accessory dwelling unit per LAMC 12.22 A.33(c) and (d). All work per engineered design.
Permit Issued
Issued on 4/21/2021
Issuing Office
Current Status
CofO Issued on 2/28/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/14/2020 APPLICANT
Assigned to Plan Check Engineer 2/19/2020 JASON JANGADA
Corrections Issued 3/13/2020 JASON JANGADA
Quality Review Completed 3/24/2020 CHRISTOPHER KOMANCHECK
Green Plans Picked Up 9/11/2020 APPLICANT
Applicant returned to address corrections 1/22/2021 JASON JANGADA
Applicant returned to address corrections 2/22/2021 JASON JANGADA
Building Plans Picked Up 2/24/2021 APPLICANT
Plan Check Approved 4/5/2021 JASON JANGADA
Issued 4/21/2021 APPLICANT
CofO in Progress 2/27/2024 ALIZAH MAYAGOITIA
CofO Issued 2/28/2024 DEROLD HAUFF
Permit Finaled 2/28/2024 DEROLD HAUFF

Permit Application Clearance Information

GPI Written Notices Cleared 3/24/2020 JASON JANGADA
Grading Pre-Inspection Cleared 3/24/2020 JASON JANGADA
Low Impact Development Cleared 7/15/2020 MARTIN FRAGOSO
Green Code Cleared 8/25/2020 DONALD CRICHLOW
Hydrant and Access approval Cleared 9/29/2020 MATTHEW CRAIG
Address approval Cleared 10/28/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 10/29/2020 CECILIO NAVARRO
Sewer availability Cleared 10/29/2020 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 12/23/2020 CECILIO NAVARRO
Highway dedication Cleared 12/24/2020 CECILIO NAVARRO

Contact Information

Contractor Ballard Nick Construction; Lic. No.: 1010094-B 8017 CRENSHAW BLVD      INGLEWOOD, CA 90305
Engineer Singh,, Jasbir; Lic. No.: C38767 16194 EASTRIDGE CT      CHINO HILLS, CA 91709

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/14/2021 Partial Approval COREY HUPP
Excavation/Setback/Form/Re-Bar 5/28/2021 Conditional Approval JOEL WILLIAMS
BUILDING-Rough-Frame 8/6/2021 Corrections Issued SCOTT FINNILA
Green Building Rough 8/6/2021 Partial Inspection SCOTT FINNILA
MERV13>=Rough 8/6/2021 Partial Inspection SCOTT FINNILA
BUILDING-Rough-Frame 9/14/2021 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 9/14/2021 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 9/14/2021 Approved CRAIG VAUGHAN
MERV13>=Rough 9/14/2021 Approved CRAIG VAUGHAN
PLUMBING-Rough 9/14/2021 Approved CRAIG VAUGHAN
Deputy Drilled-In Anchors 9/17/2021 No Access for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 9/17/2021 Approved COREY HUPP
HVAC-Rough 9/17/2021 Not Ready for Inspection COREY HUPP
Deputy Wood Construction 9/20/2021 No Access for Inspection CRAIG VAUGHAN
Pre-Inspection 9/27/2021 Corrections Issued CRAIG VAUGHAN
Underground Mechanical 9/27/2021 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 9/8/2022 Partial Inspection SCOTT FINNILA
BUILDING-Rough-Frame 9/26/2022 Corrections Issued KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 9/28/2022 Approved CRAIG VAUGHAN
Wood Frame 9/28/2022 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 10/13/2022 Approved CRAIG VAUGHAN
Insulation 10/13/2022 Not Ready for Inspection CRAIG VAUGHAN
Interior/Exterior Lathing 10/13/2022 Not Ready for Inspection CRAIG VAUGHAN
Interior/Exterior Lathing 11/7/2022 Not Ready for Inspection CRAIG VAUGHAN
Insulation 11/23/2022 No Access for Inspection CRAIG VAUGHAN
Insulation 12/2/2022 No Access for Inspection KATHRYN BUTTERWORTH
Insulation 12/9/2022 Approved AMY COLIN
Insulation 12/15/2022 Approved OSVALDO PARAMO
Drywall Nailing 1/13/2023 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 1/13/2023 Partial Approval KATHRYN BUTTERWORTH
Final 11/27/2023 Corrections Issued ROY SPAULDING
Footing/Foundation/Slab 11/27/2023 Approved ROY SPAULDING
Green Building Final 11/27/2023 Partial Approval ROY SPAULDING
MERV13>=Final 11/27/2023 Corrections Issued ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 11/27/2023 SGSOV Not Ready ROY SPAULDING
Smoke Detectors 11/27/2023 Approved ROY SPAULDING
Final 2/26/2024 OK to Issue CofO ALIZAH MAYAGOITIA
Green Building Final 2/26/2024 Approved ALIZAH MAYAGOITIA
MERV13>=Final 2/26/2024 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 2/26/2024 SGSOV Approved ALIZAH MAYAGOITIA
Service/Power Release 2/27/2024 Approved ALIZAH MAYAGOITIA