1140 N ANGELO DR 90210
Certificate Information: 1140 N ANGELO DR 90210
- Application / Permit
- 20014-30001-05281
- Plan Check / Job No.
- B21WL02851
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Supplemental ref to pcis # 20014-20000-05281, for addition and alteration to (E) SFD per engineering design and change of contractor
- Permit Issued
- Issued on 8/31/2021
- Issuing Office
- Current Status
- Permit Finaled on 9/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2021 | ALFREDO JARA |
| Corrections Issued | 6/29/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 7/14/2021 | JASON JANGADA |
| Applicant returned to address corrections | 7/28/2021 | JASON JANGADA |
| Applicant returned to address corrections | 8/5/2021 | JASON JANGADA |
| Plan Check Approved | 8/20/2021 | JASON JANGADA |
| Issued | 8/31/2021 | APPLICANT |
| Permit Finaled | 9/2/2022 | GERMAN RODRIGUEZ MENDOZA |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/20/2021 | ALFREDO JARA |
Contact Information
| Contractor | Rjc Builders Inc; Lic. No.: 740011-B | 3017 SANTA MONICA BLVD #303 SANTA MONICA, CA 90404 |
| Engineer | Moser,, Bradley Charles; Lic. No.: C68803 | 116 OAKSIDE LN BUELLTON, CA 93427 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/1/2021 | Conditional Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 9/2/2021 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 9/2/2021 | Partial Approval | CARLOS MATAMOROS |
| Underground Mechanical | 9/2/2021 | Approved | CARLOS MATAMOROS |
| Deputy Other (see comments) | 9/13/2021 | Partial Approval | MATT KELLERMAN |
| Deputy Drilled-In Anchors | 9/15/2021 | Conditional Approval | MATT KELLERMAN |
| BUILDING-Rough-Frame | 10/1/2021 | Partial Approval | MATT KELLERMAN |
| ELECTRICAL-Rough | 10/1/2021 | Not Ready for Inspection | MATT KELLERMAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2021 | Partial Approval | MATT KELLERMAN |
| Green Building Rough | 10/1/2021 | Partial Approval | MATT KELLERMAN |
| PLUMBING-Rough | 10/1/2021 | Not Ready for Inspection | MATT KELLERMAN |
| ELECTRICAL-Rough | 10/4/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Rough | 10/4/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 10/7/2021 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 10/7/2021 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 10/7/2021 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 10/7/2021 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 10/7/2021 | Approved | CARLOS MATAMOROS |
| Insulation | 4/20/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Drywall Nailing | 5/10/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 9/2/2022 | Permit Finaled | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 9/2/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Green Building Final | 9/2/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Smoke Detectors | 9/2/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |