215 N SALTAIR AVE 90049
Certificate Information: 215 N SALTAIR AVE 90049
- Application / Permit
- 20014-30000-05760
- Plan Check / Job No.
- B20WL05635
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 25' X 19' STEEL FRAMED OPEN PATIO PER ENGINEER. SEE COMMENTS.
- Permit Issued
- Issued on 4/13/2021
- Issuing Office
- Current Status
- CofO Issued on 8/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2021 | JASON JANGADA |
| Corrections Issued | 1/12/2021 | JASON JANGADA |
| Applicant returned to address corrections | 3/3/2021 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 3/19/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 3/23/2021 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 3/23/2021 | APPLICANT |
| Issued | 4/13/2021 | APPLICANT |
| CofO in Progress | 8/2/2021 | CARLOS MATAMOROS |
| Permit Finaled | 8/6/2021 | RONALD MYRICK |
| CofO Issued | 8/6/2021 | RONALD MYRICK |
| Permit Finaled | 8/6/2021 | RONALD MYRICK |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/23/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2021 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 3/3/2021 | JASON JANGADA |
Contact Information
| Contractor | J Stuart Hilliard Inc; Lic. No.: 182031-B | 7136 HASKELL AVENUE SUITE 109 VAN NUYS, CA 91406 |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/20/2021 | Conditional Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 4/21/2021 | Approved | CARLOS MATAMOROS |
| Pre-Inspection | 5/17/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 6/1/2021 | Conditional Approval | CARLOS MATAMOROS |
| Final | 6/1/2021 | Corrections Issued | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 6/1/2021 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 6/1/2021 | Approved | CARLOS MATAMOROS |
| Final | 7/8/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Light Gage Steel Frame | 7/8/2021 | Corrections Issued | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 7/23/2021 | Approved | CARLOS MATAMOROS |
| Final | 7/23/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Final | 8/2/2021 | OK to Issue CofO | CARLOS MATAMOROS |