1015 S AMHERST AVE 90049
Certificate Information: 1015 S AMHERST AVE 90049
- Application / Permit
- 20014-30000-05753
- Plan Check / Job No.
- B20WL05628
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- AN ADDITION TO CREATE A (N) DINING RM. CONVERSION OF THE (E) DINING RM INTO A LAUNDRY ROOM. GUEST BATHROOM REMODEL. ALL WORK TO COMPLY PER WFPP.
- Permit Issued
- Issued on 3/31/2021
- Issuing Office
- Current Status
- CofO Issued on 10/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2021 | RICHARD GARCIA |
| Corrections Issued | 1/10/2021 | RICHARD GARCIA |
| Applicant returned to address corrections | 2/22/2021 | RICHARD GARCIA |
| Building Plans Picked Up | 2/24/2021 | APPLICANT |
| Applicant returned to address corrections | 3/12/2021 | RICHARD GARCIA |
| Plan Check Approved | 3/23/2021 | RICHARD GARCIA |
| Issued | 3/31/2021 | APPLICANT |
| CofO in Progress | 8/23/2021 | KENNETH NAGLE |
| Permit Finaled | 10/6/2021 | KENNETH NAGLE |
| CofO Issued | 10/6/2021 | KENNETH NAGLE |
| Permit Finaled | 10/6/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/3/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2021 | DINAH GARIN |
Contact Information
| Contractor | Davinci Design + Construction; Lic. No.: 1063652-B | 928 21ST STREET #1 SANTA MONICA, CA 90403 |
| Engineer | Reyes,, Jose E; Lic. No.: C70677 | 1219 E ADAMS BLVD LOS ANGELES, CA 90011 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/5/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 4/7/2021 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 4/13/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 5/14/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Rough | 5/14/2021 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 5/14/2021 | Corrections Issued | KEVIN SARGSYAN |
| Pre-Inspection | 5/14/2021 | Partial Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 5/18/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 5/18/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 5/18/2021 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 5/20/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 5/20/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 5/21/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 5/28/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Green Building Rough | 5/28/2021 | Approved | OGANES TARAKHCHYAN |
| Insulation | 5/28/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Shower Pan | 5/28/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Insulation | 6/2/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Shower Pan | 6/2/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Special/Order Compliance | 6/2/2021 | Corrections Issued | OGANES TARAKHCHYAN |
| Drywall Nailing | 6/7/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Shower Pan | 6/8/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Shower Pan | 6/18/2021 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 6/28/2021 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 7/13/2021 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 7/13/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 7/13/2021 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 7/19/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Final | 7/19/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Final | 7/19/2021 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 7/20/2021 | Approved | OGANES TARAKHCHYAN |
| Final | 7/20/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 7/20/2021 | Approved | OGANES TARAKHCHYAN |
| Green Building Final | 7/20/2021 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 7/20/2021 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 7/20/2021 | Approved | OGANES TARAKHCHYAN |
| Final | 8/3/2021 | Conditional Approval | OGANES TARAKHCHYAN |