243 N NORTON AVE 90004
Certificate Information: 243 N NORTON AVE 90004
- Application / Permit
- 20014-30000-05733
- Plan Check / Job No.
- B20WL05608
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior remodel & 1st & 2nd story addition at rear of (E) 2 story SFD.
- Permit Issued
- Issued on 7/9/2021
- Issuing Office
- Current Status
- CofO Issued on 3/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 2/21/2021 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 3/2/2021 | TARIK SAOUD |
| Plan Check Approved | 4/28/2021 | TARIK SAOUD |
| Issued | 7/9/2021 | APPLICANT |
| CofO in Progress | 2/7/2023 | JEFFREY MEAD |
| Permit Finaled | 3/2/2023 | DEROLD HAUFF |
| CofO Issued | 3/2/2023 | DEROLD HAUFF |
| Permit Finaled | 3/2/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/23/2021 | JEANIE LAM |
| Sewer availability | Cleared | 3/23/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2021 | JEANIE LAM |
| CPC | Cleared | 4/12/2021 | LYDIA CHAPMAN |
Contact Information
| Contractor | Numa Brothers Construction Inc; Lic. No.: 859857-B | 18375 VENTURA BLVD #270 TARZANA, CA 91356 |
| Engineer | Galbreath,, Sean Martin; Lic. No.: S5653 | 600 SOUTH LAKE AVE STE 308 PASADENA, CA 91106 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/13/2021 | Partial Approval | JOSEPH MCGARRY |
| Wood Frame | 8/5/2021 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 8/23/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 8/23/2021 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 9/7/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Rough | 9/7/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 9/13/2021 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2021 | Partial Approval | JOSEPH MCGARRY |
| HVAC-Rough | 9/13/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 9/17/2021 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 10/29/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Rough | 10/29/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 12/8/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 12/8/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 12/8/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 12/10/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 12/10/2021 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 12/10/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Insulation | 12/14/2021 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 3/9/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Drywall Nailing | 3/14/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Drywall Nailing | 12/5/2022 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 12/5/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Footing/Foundation/Slab | 12/5/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Final | 12/5/2022 | Not Ready for Inspection | JEFFREY MEAD |
| HVAC-Final | 12/5/2022 | Not Ready for Inspection | JEFFREY MEAD |
| PLUMBING-Final | 12/5/2022 | Not Ready for Inspection | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 12/5/2022 | SGSOV Not Ready | JEFFREY MEAD |
| Smoke Detectors | 12/5/2022 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Final | 12/28/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 12/28/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Footing/Foundation/Slab | 12/28/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Final | 12/28/2022 | Not Ready for Inspection | JEFFREY MEAD |
| HVAC-Final | 12/28/2022 | Not Ready for Inspection | JEFFREY MEAD |
| PLUMBING-Final | 12/28/2022 | Not Ready for Inspection | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 12/28/2022 | SGSOV Not Ready | JEFFREY MEAD |
| Smoke Detectors | 12/28/2022 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Final | 2/2/2023 | Approved | JEFFREY MEAD |
| Final | 2/2/2023 | Corrections Issued | JEFFREY MEAD |
| Footing/Foundation/Slab | 2/2/2023 | Approved | JEFFREY MEAD |
| Green Building Final | 2/2/2023 | Approved | JEFFREY MEAD |
| HVAC-Final | 2/2/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 2/2/2023 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 2/2/2023 | SGSOV Not Ready | JEFFREY MEAD |
| Smoke Detectors | 2/2/2023 | Approved | JEFFREY MEAD |
| Final | 2/6/2023 | OK to Issue CofO | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 2/6/2023 | SGSOV Approved | JEFFREY MEAD |