4928 N ODESSA AVE 91436

Certificate Information: 4928 N ODESSA AVE 91436

Application / Permit
20014-30000-05721
Plan Check / Job No.
B20WL05597
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior alteration and ground floor addition to an existing SFD with attached 2-car garage.
Permit Issued
Issued on 8/2/2021
Issuing Office
Current Status
CofO Issued on 3/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2020 APPLICANT
Assigned to Plan Check Engineer 1/7/2021 KAVIAN REFAHI
Corrections Issued 1/9/2021 KAVIAN REFAHI
Building Plans Picked Up 1/15/2021 APPLICANT
Applicant returned to address corrections 5/7/2021 JASON JANGADA
Plan Check Approved 5/21/2021 JASON JANGADA
Issued 8/2/2021 APPLICANT
CofO in Progress 2/16/2023 VINCENT HANLEY
Permit Finaled 3/23/2023 JOHN JANSON
CofO Issued 3/23/2023 JOHN JANSON
Permit Finaled 3/23/2023 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/28/2021 GABRIEL ROBLES
Permit Cleared 1/28/2021 GABRIEL ROBLES
Sewer availability Cleared 1/28/2021 GABRIEL ROBLES
Trees in Parkway Cleared 3/3/2021 JOHN KIM
Low Impact Development Cleared 4/29/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 4/29/2021 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,
Engineer Sveiven,, Shane; Lic. No.: C89133 5900 CANTERBURY DR APT A206      CULVER CITY, CA 90230

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/30/2021 Approved ROBERT GOLD
Excavation/Setback/Form/Re-Bar 12/6/2021 Corrections Issued ROBERT GOLD
Deputy Drilled-In Anchors 12/28/2021 Conditional Approval RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 1/6/2022 Partial Inspection DAVID SANDOVAL
Excavation/Setback/Form/Re-Bar 1/28/2022 Partial Inspection ROBERT GOLD
Deputy Drilled-In Anchors 2/23/2022 Conditional Approval JESUS PINEDA
Footing/Foundation/Slab 3/18/2022 Approved ROBERT GOLD
BUILDING-Rough-Frame 5/26/2022 Partial Inspection ROBERT GOLD
PLUMBING-Rough 5/27/2022 Partial Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 6/6/2022 Corrections Issued HENRY KIM
Insulation 6/6/2022 Partial Approval HENRY KIM
BUILDING-Rough-Frame 6/7/2022 Partial Approval ROBERT GOLD
Green Building Rough 6/7/2022 Not Ready for Inspection ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 8/4/2022 Partial Approval VINCENT HANLEY
Deputy Wood Construction 8/12/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 8/26/2022 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 8/26/2022 Approved VINCENT HANLEY
Green Building Rough 8/26/2022 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 8/26/2022 Approved VINCENT HANLEY
PLUMBING-Rough 8/26/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 9/21/2022 Approved VINCENT HANLEY
Green Building Rough 9/21/2022 Approved VINCENT HANLEY
Insulation 10/7/2022 Approved MORRIS JACKSON
Interior/Exterior Lathing 10/7/2022 Partial Approval MORRIS JACKSON
Drywall Nailing 10/20/2022 Approved JESUS PINEDA
Shower Pan 10/28/2022 Approved MORRIS JACKSON
Interior/Exterior Lathing 11/2/2022 Approved VINCENT HANLEY
ELECTRICAL-Final 2/15/2023 Approved VINCENT HANLEY
Final 2/15/2023 OK to Issue CofO VINCENT HANLEY
Gas Test 2/15/2023 Approved VINCENT HANLEY
Green Building Final 2/15/2023 Approved VINCENT HANLEY
HVAC-Final 2/15/2023 Approved VINCENT HANLEY
PLUMBING-Final 2/15/2023 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 2/15/2023 SGSOV Approved VINCENT HANLEY
Smoke Detectors 2/15/2023 Approved VINCENT HANLEY