1660 S STANLEY AVE 90019

Certificate Information: 1660 S STANLEY AVE 90019

Application / Permit
20014-30000-05720
Plan Check / Job No.
B20WL05594
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) garage (293.6 sq ft) to ADU with addition (188.0 sq ft).
Permit Issued
Issued on 5/28/2021
Issuing Office
Current Status
CofO Issued on 3/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/10/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 RICHARD GARCIA
Corrections Issued 2/20/2021 RICHARD GARCIA
Applicant returned to address corrections 4/10/2021 RICHARD GARCIA
Applicant returned to address corrections 4/27/2021 DAVID CASTILLO
Applicant returned to address corrections 5/6/2021 DAVID CASTILLO
Plan Check Approved 5/18/2021 DAVID CASTILLO
Issued 5/28/2021 APPLICANT
CofO in Progress 6/21/2022 JOSE AVILA
Permit Finaled 3/8/2023 DANIEL ORRANTE
CofO Issued 3/8/2023 DANIEL ORRANTE
Permit Finaled 3/8/2023 DANIEL ORRANTE

Permit Application Clearance Information

ZI Cleared 3/1/2021 MAXFIELD VERMY
ZI Cleared 3/1/2021 MAXFIELD VERMY
Address approval Cleared 3/2/2021 JEANIE LAM
Sewer availability Cleared 3/15/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/30/2021 JEANIE LAM
Hydrant and Access approval Cleared 4/21/2021 JOHN CONNEALLY
Roof/Waste drainage to street Cleared 5/10/2021 JEANIE LAM

Contact Information

Contractor Rimon Adam; Lic. No.: 935565-B 554 SAN VICENTE BLVD      LOS ANGELES, CA 90042
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22121 CLARENDON ST APT 340      WOODLAND HILLS, CA 91367

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/19/2021 Partial Approval CHRISTOPHER DELLEFIELD
Sewer 7/19/2021 Approved CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 7/23/2021 Partial Approval STUART CHAPMAN
METHANE-Barrier 7/23/2021 Approved STUART CHAPMAN
METHANE-Subgrade 7/23/2021 Approved STUART CHAPMAN
Deputy Drilled-In Anchors 7/30/2021 Approved JUSTIN HAWLEY
Deputy Drilled-In Anchors 8/3/2021 Partial Approval RUBEN SALAS
Footing/Foundation/Slab 8/5/2021 Partial Approval HORACE FULTZ
Deputy Reinf. Concrete 8/9/2021 Partial Approval RUBEN SALAS
Deputy Drilled-In Anchors 8/25/2021 Conditional Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 8/27/2021 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 8/27/2021 Approved STUART CHAPMAN
Deputy Reinf. Concrete 8/31/2021 Conditional Approval CALEB MEISTER
ELECTRICAL-Rough 10/6/2021 Corrections Issued SCOTT FINNILA
Shower Pan 10/6/2021 Approved SCOTT FINNILA
Underground Mechanical 10/6/2021 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 10/25/2021 Not Ready for Inspection JOSE AVILA
ELECTRICAL-Rough 10/25/2021 Approved JOSE AVILA
Green Building Rough 10/25/2021 Approved JOSE AVILA
HVAC-Rough 10/25/2021 Approved JOSE AVILA
METHANE-Rough 10/25/2021 Corrections Issued JOSE AVILA
PLUMBING-Rough 10/25/2021 Corrections Issued JOSE AVILA
PLUMBING-Rough 10/25/2021 Partial Inspection SCOTT FINNILA
PLUMBING-Rough 10/27/2021 Approved JOSE AVILA
Insulation 11/3/2021 Approved JOSE AVILA
Interior/Exterior Lathing 11/3/2021 Approved JOSE AVILA
Drywall Nailing 11/8/2021 Approved JOSE AVILA
BUILDING-Rough-Frame 1/31/2022 Approved JOSE AVILA
ELECTRICAL-Final 1/31/2022 Corrections Issued JOSE AVILA
Final 1/31/2022 Not Ready for Inspection JOSE AVILA
Green Building Final 1/31/2022 Corrections Issued JOSE AVILA
HVAC-Final 1/31/2022 Corrections Issued JOSE AVILA
METHANE-Final 1/31/2022 Approved JOSE AVILA
METHANE-Rough 1/31/2022 Approved JOSE AVILA
PLUMBING-Final 1/31/2022 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 1/31/2022 SGSOV Not Ready JOSE AVILA
Service/Power Release 1/31/2022 Not Ready for Inspection JOSE AVILA
Smoke Detectors 1/31/2022 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 2/4/2022 SGSOV Not Ready JOSE AVILA
ELECTRICAL-Final 2/11/2022 Approved JOSE AVILA
Final 2/11/2022 Corrections Issued JOSE AVILA
Green Building Final 2/11/2022 Approved JOSE AVILA
HVAC-Final 2/11/2022 Approved JOSE AVILA
PLUMBING-Final 2/11/2022 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 2/11/2022 SGSOV Approved JOSE AVILA
Service/Power Release 2/11/2022 Approved JOSE AVILA
ELECTRICAL-Final 3/9/2022 Approved JOSE AVILA
Final 3/9/2022 Not Ready for Inspection JOSE AVILA
HVAC-Final 3/9/2022 Approved JOSE AVILA
PLUMBING-Final 3/9/2022 Approved JOSE AVILA
Service/Power Release 3/9/2022 Approved JOSE AVILA
Final 6/20/2022 OK to Issue CofO JOSE AVILA