1909 S MIDVALE AVE 90025
Certificate Information: 1909 S MIDVALE AVE 90025
- Application / Permit
- 20014-30000-05688
- Plan Check / Job No.
- B20WL05571
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) STORAGE ROOM INTO AN ADU WITH AN ADDITION PER WFPP & CA G.C.S. 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c)(d)AND (g).
- Permit Issued
- Issued on 11/3/2022
- Issuing Office
- Current Status
- CofO Issued on 9/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2021 | MARJAN SHENASI |
| Corrections Issued | 1/23/2021 | MARJAN SHENASI |
| Applicant returned to address corrections | 10/6/2022 | RICHARD GARCIA |
| Plan Check Approved | 10/24/2022 | JAHANSHAH POURHASSAN |
| Issued | 11/3/2022 | APPLICANT |
| Building Plans Picked Up | 11/9/2022 | APPLICANT |
| CofO in Progress | 8/23/2024 | KIRK SANDERS |
| Permit Finaled | 9/7/2024 | RICHARD STEINBACH |
| CofO Issued | 9/7/2024 | RICHARD STEINBACH |
| Permit Finaled | 9/7/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Construction within easement | Cleared | 2/11/2021 | WALTER RAMIREZ |
| Specific Plan | Cleared | 3/4/2021 | WESTON PRINGLE |
| Address approval | Cleared | 3/9/2021 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 4/7/2021 | KIRK LINKLATER |
| Miscellaneous | Cleared | 7/25/2022 | JENSON LEE |
| Low Impact Development | Cleared | 8/16/2022 | ANTHONY VARGAS |
| Hydrant and Access approval | Cleared | 8/31/2022 | GILBERT URREA |
| Roof/Waste drainage to street | Cleared | 9/27/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/3/2022 | DINAH GARIN |
| Sewer availability | Cleared | 10/3/2022 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/27/2023 | Partial Approval | CLAYTON GRAHAM |
| Special/Order Compliance | 2/27/2023 | Partial Inspection | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 3/31/2023 | Corrections Issued | CLAYTON GRAHAM |
| Underground Mechanical | 3/31/2023 | Partial Approval | CLAYTON GRAHAM |
| Footing/Foundation/Slab | 5/25/2023 | Not Ready for Inspection | JESUS PINEDA |
| Footing/Foundation/Slab | 6/6/2023 | Approved | JESUS PINEDA |
| Footing/Foundation/Slab | 6/21/2023 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2023 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 9/22/2023 | Corrections Issued | BEN MOLSTAD |
| Gas Test | 9/22/2023 | Partial Approval | BEN MOLSTAD |
| HVAC-Rough | 9/22/2023 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Rough | 9/22/2023 | Corrections Issued | BEN MOLSTAD |
| Sewer | 9/26/2023 | Partial Approval | CHRISTOPHER WILSON |
| Underground Mechanical | 9/26/2023 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 9/28/2023 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 9/28/2023 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 9/28/2023 | Approved | ARAM AVEDISIAN |
| Special/Order Compliance | 9/28/2023 | Corrections Issued | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 10/3/2023 | Approved | BEN MOLSTAD |
| Green Building Rough | 10/3/2023 | Approved | BEN MOLSTAD |
| Insulation | 10/3/2023 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 10/3/2023 | Approved | BEN MOLSTAD |
| Shower Pan | 10/3/2023 | Approved | BEN MOLSTAD |
| Drywall Nailing | 10/11/2023 | Approved | BEN MOLSTAD |
| Drywall Nailing | 10/13/2023 | No Access for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 2/7/2024 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 2/12/2024 | Not Ready for Inspection | JESUS PINEDA |
| Service/Power Release | 2/12/2024 | Not Ready for Inspection | JESUS PINEDA |
| Final | 6/24/2024 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 6/24/2024 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 6/24/2024 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 6/24/2024 | Approved | KIRK SANDERS |
| Final | 8/14/2024 | Corrections Issued | KIRK SANDERS |
| Service/Power Release | 8/14/2024 | Corrections Issued | KIRK SANDERS |
| Final | 8/19/2024 | OK to Issue CofO | KIRK SANDERS |