1909 S MIDVALE AVE 90025

Certificate Information: 1909 S MIDVALE AVE 90025

Application / Permit
20014-30000-05688
Plan Check / Job No.
B20WL05571
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) STORAGE ROOM INTO AN ADU WITH AN ADDITION PER WFPP & CA G.C.S. 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c)(d)AND (g).
Permit Issued
Issued on 11/3/2022
Issuing Office
Current Status
CofO Issued on 9/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/13/2021 APPLICANT
Assigned to Plan Check Engineer 1/21/2021 MARJAN SHENASI
Corrections Issued 1/23/2021 MARJAN SHENASI
Applicant returned to address corrections 10/6/2022 RICHARD GARCIA
Plan Check Approved 10/24/2022 JAHANSHAH POURHASSAN
Issued 11/3/2022 APPLICANT
Building Plans Picked Up 11/9/2022 APPLICANT
CofO in Progress 8/23/2024 KIRK SANDERS
Permit Finaled 9/7/2024 RICHARD STEINBACH
CofO Issued 9/7/2024 RICHARD STEINBACH
Permit Finaled 9/7/2024 RICHARD STEINBACH

Permit Application Clearance Information

Construction within easement Cleared 2/11/2021 WALTER RAMIREZ
Specific Plan Cleared 3/4/2021 WESTON PRINGLE
Address approval Cleared 3/9/2021 DINAH GARIN
Grading Pre-Inspection Cleared 4/7/2021 KIRK LINKLATER
Miscellaneous Cleared 7/25/2022 JENSON LEE
Low Impact Development Cleared 8/16/2022 ANTHONY VARGAS
Hydrant and Access approval Cleared 8/31/2022 GILBERT URREA
Roof/Waste drainage to street Cleared 9/27/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 10/3/2022 DINAH GARIN
Sewer availability Cleared 10/3/2022 DINAH GARIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/27/2023 Partial Approval CLAYTON GRAHAM
Special/Order Compliance 2/27/2023 Partial Inspection DAVID FEILER
Excavation/Setback/Form/Re-Bar 3/31/2023 Corrections Issued CLAYTON GRAHAM
Underground Mechanical 3/31/2023 Partial Approval CLAYTON GRAHAM
Footing/Foundation/Slab 5/25/2023 Not Ready for Inspection JESUS PINEDA
Footing/Foundation/Slab 6/6/2023 Approved JESUS PINEDA
Footing/Foundation/Slab 6/21/2023 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 6/28/2023 Approved JESUS PINEDA
ELECTRICAL-Rough 9/22/2023 Corrections Issued BEN MOLSTAD
Gas Test 9/22/2023 Partial Approval BEN MOLSTAD
HVAC-Rough 9/22/2023 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Rough 9/22/2023 Corrections Issued BEN MOLSTAD
Sewer 9/26/2023 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 9/26/2023 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 9/28/2023 Approved ARAM AVEDISIAN
HVAC-Rough 9/28/2023 Approved ARAM AVEDISIAN
PLUMBING-Rough 9/28/2023 Approved ARAM AVEDISIAN
Special/Order Compliance 9/28/2023 Corrections Issued ARAM AVEDISIAN
BUILDING-Rough-Frame 10/3/2023 Approved BEN MOLSTAD
Green Building Rough 10/3/2023 Approved BEN MOLSTAD
Insulation 10/3/2023 Approved BEN MOLSTAD
Interior/Exterior Lathing 10/3/2023 Approved BEN MOLSTAD
Shower Pan 10/3/2023 Approved BEN MOLSTAD
Drywall Nailing 10/11/2023 Approved BEN MOLSTAD
Drywall Nailing 10/13/2023 No Access for Inspection BEN MOLSTAD
ELECTRICAL-Final 2/7/2024 Corrections Issued TEMISTOCLES CAAL
ELECTRICAL-Final 2/12/2024 Not Ready for Inspection JESUS PINEDA
Service/Power Release 2/12/2024 Not Ready for Inspection JESUS PINEDA
Final 6/24/2024 Corrections Issued KIRK SANDERS
Green Building Final 6/24/2024 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 6/24/2024 SGSOV Approved KIRK SANDERS
Smoke Detectors 6/24/2024 Approved KIRK SANDERS
Final 8/14/2024 Corrections Issued KIRK SANDERS
Service/Power Release 8/14/2024 Corrections Issued KIRK SANDERS
Final 8/19/2024 OK to Issue CofO KIRK SANDERS