2062 S KERWOOD AVE 90025

Certificate Information: 2062 S KERWOOD AVE 90025

Application / Permit
20014-30000-05654
Plan Check / Job No.
B20WL05522
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-story addition w/ roof trusses
Permit Issued
Issued on 3/3/2021
Issuing Office
Current Status
CofO Issued on 3/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/18/2020 APPLICANT
Assigned to Plan Check Engineer 12/21/2020 DAVID CASTILLO
Corrections Issued 12/24/2020 DAVID CASTILLO
Quality Review Completed 1/8/2021 TARIK SAOUD
Plan Check Approved 3/3/2021 DAVID CASTILLO
Issued 3/3/2021 APPLICANT
Building Plans Picked Up 3/5/2021 APPLICANT
CofO in Progress 1/31/2022 BRENDAN LOONEY
No Progress 2/3/2022 MICHAEL PELHAM
CofO in Progress 3/1/2022 MICHAEL PELHAM
Permit Finaled 3/1/2022 DANIEL ORRANTE
CofO Issued 3/1/2022 DANIEL ORRANTE
Permit Finaled 3/1/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/21/2021 DINAH GARIN
Permit Cleared 1/21/2021 DINAH GARIN
Sewer availability Cleared 1/22/2021 DINAH GARIN
Trees in Parkway Cleared 1/25/2021 JOHN KIM
Low Impact Development Cleared 2/10/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 2/25/2021 DINAH GARIN
Demolition Pre-Inspection Cleared 3/3/2021 DAVID CASTILLO
Grading Pre-Inspection Cleared 3/3/2021 DAVID CASTILLO

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/15/2021 Partial Inspection GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 4/30/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Underground Mechanical 4/30/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Drilled-In Anchors 5/21/2021 Conditional Approval WILLIAM ROSE
Excavation/Setback/Form/Re-Bar 5/24/2021 Approved MATT KELLERMAN
Footing/Foundation/Slab 5/24/2021 Approved MATT KELLERMAN
METHANE-Barrier 5/24/2021 Approved MATT KELLERMAN
METHANE-Subgrade 5/24/2021 Approved MATT KELLERMAN
Deputy Reinf. Concrete 5/25/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 6/7/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Wood Construction 6/8/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 6/29/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 7/30/2021 Approved KIM BEAUCHAMP
HVAC-Rough 7/30/2021 Corrections Issued KIM BEAUCHAMP
Interior/Exterior Lathing 8/5/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
METHANE-Rough 8/5/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 8/5/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Deputy Wood Construction 8/17/2021 Conditional Approval DANIEL ORRANTE
Interior/Exterior Lathing 8/17/2021 Approved JESUS RODRIGUEZ
Special/Order Compliance 8/17/2021 Partial Inspection SHAVONNE ESPINOZA
Interior/Exterior Lathing 8/19/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 8/19/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Shower Pan 8/19/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 9/8/2021 Approved GERMAN RODRIGUEZ MENDOZA
Sewer 9/8/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Shower Pan 9/8/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Deputy Wood Construction 9/10/2021 Conditional Approval MORRIS JACKSON
Sewer 9/16/2021 Approved GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 9/23/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Green Building Rough 9/23/2021 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 9/23/2021 Approved GERMAN RODRIGUEZ MENDOZA
METHANE-Rough 9/23/2021 Approved GERMAN RODRIGUEZ MENDOZA
Deputy Wood Construction 9/24/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 9/30/2021 Approved GERMAN RODRIGUEZ MENDOZA
Deputy Drilled-In Anchors 9/30/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Insulation 9/30/2021 Approved GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 10/7/2021 Approved DEANDRE HOFFMAN
Interior/Exterior Lathing 10/15/2021 Approved DEANDRE HOFFMAN
Shower Pan 10/15/2021 Approved DEANDRE HOFFMAN
ELECTRICAL-Final 12/9/2021 No Access for Inspection BRENDAN LOONEY
ELECTRICAL-Final 12/15/2021 Corrections Issued BRENDAN LOONEY
HVAC-Final 12/15/2021 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Final 12/22/2021 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Final 12/22/2021 Corrections Issued BRENDAN LOONEY
Service/Power Release 12/22/2021 Not Ready for Inspection BRENDAN LOONEY
ELECTRICAL-Final 12/28/2021 Approved CHRISTOPHER WILSON
HVAC-Final 12/28/2021 Not Ready for Inspection CHRISTOPHER WILSON
HVAC-Final 1/11/2022 Approved BRENDAN LOONEY
PLUMBING-Final 1/11/2022 Partial Approval BRENDAN LOONEY
PLUMBING-Rough 1/12/2022 Not Ready for Inspection BRENDAN LOONEY
Final 1/14/2022 Corrections Issued BRENDAN LOONEY
Green Building Final 1/14/2022 Approved BRENDAN LOONEY
PLUMBING-Final 1/14/2022 Approved BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 1/14/2022 SGSOV Approved BRENDAN LOONEY
Smoke Detectors 1/14/2022 Approved BRENDAN LOONEY
Final 1/20/2022 Not Ready for Inspection BRENDAN LOONEY
Final 1/28/2022 OK to Issue CofO BRENDAN LOONEY
Service/Power Release 1/28/2022 Approved BRENDAN LOONEY