23601 W BALTAR ST 91304

Certificate Information: 23601 W BALTAR ST 91304

Application / Permit
20014-30000-05623
Plan Check / Job No.
B20WL05496
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition/remodel to kitchen and family room at first floor of existing 2-story single family home.
Permit Issued
Issued on 3/17/2022
Issuing Office
Current Status
CofO Issued on 8/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/22/2020 APPLICANT
Assigned to Plan Check Engineer 12/29/2020 RICHARD GARCIA
Corrections Issued 1/2/2021 RICHARD GARCIA
Plan Check Approved 2/22/2021 RICHARD GARCIA
Issued 3/17/2022 APPLICANT
Building Plans Picked Up 3/18/2022 APPLICANT
CofO in Progress 8/9/2023 JOHN KIDWELL
Permit Finaled 8/9/2023 JOHN JANSON
CofO Issued 8/9/2023 JOHN JANSON
Permit Finaled 8/9/2023 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/25/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/26/2021 ADRIAN CASTRO
ZI Cleared 1/27/2021 DENZEL HENDERSON
Grading Pre-Inspection Cleared 1/29/2021 BRIAN MILLER

Contact Information

Contractor B T C Builders Inc; Lic. No.: 743191-B 11373 W WASHINGTON BLVD      LOS ANGELES, CA 90066
Engineer Sarrami,, Gholamali F; Lic. No.: C43720 4942 HIGHLAND VIEW AVENUE      LOS ANGELES, CA 90041

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/7/2022 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 12/20/2022 Partial Approval CHRIS CHRISTENSEN
Wood Frame 12/20/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Deputy Wood Construction 12/21/2022 Conditional Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 12/28/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 12/28/2022 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 12/28/2022 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 1/3/2023 Approved CHRIS CHRISTENSEN
HVAC-Rough 1/3/2023 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 1/3/2023 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 1/17/2023 Conditional Approval CHRIS CHRISTENSEN
Green Building Rough 1/17/2023 Approved CHRIS CHRISTENSEN
Insulation 1/17/2023 Conditional Approval CHRIS CHRISTENSEN
Special/Order Compliance 1/17/2023 Partial Inspection JESUS PINEDA
Drywall Nailing 1/24/2023 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 8/3/2023 Approved CHRIS CHRISTENSEN
Final 8/3/2023 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 8/3/2023 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 8/3/2023 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 8/3/2023 Approved CHRIS CHRISTENSEN
Final 8/8/2023 OK to Issue CofO JOHN KIDWELL