414 S RIMPAU BLVD 90020

Certificate Information: 414 S RIMPAU BLVD 90020

Application / Permit
20014-30000-05588
Plan Check / Job No.
B20WL05467
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) Backyard main patio attached to the (E) guest house
Permit Issued
Issued on 6/28/2021
Issuing Office
Current Status
Issued on 6/28/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/5/2021 APPLICANT
Assigned to Plan Check Engineer 1/7/2021 RICHARD GARCIA
Corrections Issued 1/9/2021 RICHARD GARCIA
Building Plans Picked Up 1/15/2021 APPLICANT
Applicant returned to address corrections 2/11/2021 ALFREDO JARA
Applicant returned to address corrections 3/9/2021 ALFREDO JARA
Plan Check Approved 4/15/2021 RICHARD GARCIA
Issued 6/28/2021 APPLICANT

Permit Application Clearance Information

HPOZ Cleared 2/1/2021 SUKI GERSHENHORN
ZI Cleared 2/1/2021 SUKI GERSHENHORN
Miscellaneous Cleared 2/16/2021 SUKI GERSHENHORN
Miscellaneous Cleared 2/16/2021 SUKI GERSHENHORN
ZA Case Cleared 2/16/2021 SUKI GERSHENHORN
Eng Process Fee Ord 176,300 Cleared 2/17/2021 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 2/17/2021 ANTHONY MAINEZ

Contact Information

Architect Mahmoodi,, Arshia; Lic. No.: C34875 6543 FRANKLIN AVENUE # 306      LOS ANGELES, CA 90028
Contractor Caputo Construction Corporation; Lic. No.: 842817-B 8939 SOUTH SEPULVEDA BLVD   SUITE 110 - 702    LOS ANGELES, CA 90045
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/20/2021 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 7/28/2021 Approved ARTHUR SARGSYAN
METHANE-Barrier 7/28/2021 Approved ARTHUR SARGSYAN
METHANE-Subgrade 7/28/2021 Approved ARTHUR SARGSYAN
Deputy Steel/Welding 12/3/2021 Conditional Approval ADAM ESCOTO
ELECTRICAL-Rough 2/25/2022 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 7/13/2022 Not Ready for Inspection ADAM ESCOTO
Final 7/13/2022 Not Ready for Inspection ADAM ESCOTO
Green Building Final 7/13/2022 Approved ADAM ESCOTO
Green Building Rough 7/13/2022 Approved ADAM ESCOTO
METHANE-Final 7/13/2022 Approved ADAM ESCOTO
METHANE-Rough 7/13/2022 Approved ADAM ESCOTO
SGSOV-Seismic Gas S/O Valve 7/13/2022 SGSOV Approved ADAM ESCOTO
Smoke Detectors 7/13/2022 Approved ADAM ESCOTO
HVAC-Final 10/11/2023 Partial Inspection SCOTT FINNILA
Pre-Inspection 10/12/2023 Approved RICHARD DOCKUS