2916 S RIMPAU BLVD 90016
Certificate Information: 2916 S RIMPAU BLVD 90016
- Application / Permit
- 20014-30000-05565
- Plan Check / Job No.
- B20WL05448
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY ADU
- Permit Issued
- Issued on 7/22/2022
- Issuing Office
- Current Status
- Issued on 7/22/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2021 | TARIK SAOUD |
| Corrections Issued | 1/27/2021 | TARIK SAOUD |
| Quality Review Completed | 2/2/2021 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 4/29/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 10/20/2021 | TARIK SAOUD |
| Plan Check Approved | 7/8/2022 | TARIK SAOUD |
| Issued | 7/22/2022 | APPLICANT |
| Building Plans Picked Up | 7/25/2022 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/1/2021 | JUAN ASHTON |
| Address approval | Cleared | 3/17/2021 | JUAN ASHTON |
| Roof/Waste drainage to street | Cleared | 7/20/2021 | WALLIE JONG |
| Sewer availability | Cleared | 7/21/2021 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kamkar,, Albert; Lic. No.: C38311 | 12340 SANTA MONICA BLVD 236 SANTA MONICA, CA 90025 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/4/2024 | Approved | JUSTIN HAWLEY |
| Pre-Inspection | 3/5/2025 | Approved | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 4/10/2025 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Rough | 4/10/2025 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 5/6/2025 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2025 | Corrections Issued | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 12/23/2025 | Corrections Issued | JUSTIN HAWLEY |
| Gas Test | 1/14/2026 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 1/14/2026 | Partial Approval | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 1/21/2026 | Approved | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2026 | Approved | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 1/21/2026 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 4/17/2026 | Approved | JUSTIN HAWLEY |
| Insulation | 4/17/2026 | Corrections Issued | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 4/17/2026 | Partial Inspection | JUSTIN HAWLEY |
| Drywall Nailing | 6/5/2026 | Approved | ALEX COLIN |
| Insulation | 6/5/2026 | Approved | ALEX COLIN |