5720 N GEYSER AVE 91356

Certificate Information: 5720 N GEYSER AVE 91356

Application / Permit
20014-30000-05560
Plan Check / Job No.
B20WL05442
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition to SFD. Extend two bedrooms and add a bathroom, walk in closet, and powder room.
Permit Issued
Issued on 4/22/2021
Issuing Office
Current Status
CofO Issued on 3/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/15/2020 APPLICANT
Assigned to Plan Check Engineer 12/29/2020 RICHARD GARCIA
Corrections Issued 1/3/2021 RICHARD GARCIA
Applicant returned to address corrections 2/26/2021 JASON JANGADA
Building Plans Picked Up 3/1/2021 APPLICANT
Plan Check Approved 3/18/2021 MANUEL GARCIA
Issued 4/22/2021 APPLICANT
CofO in Progress 2/15/2022 SEAN HAUPT
Permit Finaled 3/11/2022 RONALD MYRICK
CofO Issued 3/11/2022 RONALD MYRICK
Permit Finaled 3/11/2022 RONALD MYRICK

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/21/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 1/21/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 1/25/2021 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer Azizisefat,, Solayman; Lic. No.: C57840 19510 VENTURA BLVD STE 110      TARZANA, CA 91356

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/6/2021 Conditional Approval STEVEN BACK
Excavation/Setback/Form/Re-Bar 7/13/2021 Approved STEVEN BACK
Footing/Foundation/Slab 7/13/2021 Approved STEVEN BACK
Insulation 7/26/2021 Partial Approval STEVEN BACK
Wood Frame 7/26/2021 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 8/27/2021 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Rough 8/27/2021 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 8/27/2021 Partial Approval STEVEN BACK
Green Building Rough 8/27/2021 Not Ready for Inspection STEVEN BACK
MERV13>=Rough 8/27/2021 Approved STEVEN BACK
PLUMBING-Rough 8/27/2021 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 9/23/2021 Approved DAVID SANDOVAL
Green Building Rough 9/23/2021 Not Ready for Inspection DAVID SANDOVAL
HVAC-Rough 9/23/2021 Corrections Issued DAVID SANDOVAL
BUILDING-Rough-Frame 9/30/2021 Approved STEVEN BACK
Green Building Rough 9/30/2021 Approved STEVEN BACK
HVAC-Rough 9/30/2021 Approved STEVEN BACK
Interior/Exterior Lathing 9/30/2021 Partial Approval STEVEN BACK
Insulation 10/7/2021 Approved STEVEN BACK
Drywall Nailing 10/21/2021 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 10/21/2021 Approved JAVIER RAMOS JR
ELECTRICAL-Final 2/15/2022 Approved SEAN HAUPT
Final 2/15/2022 OK to Issue CofO SEAN HAUPT
Green Building Final 2/15/2022 Approved SEAN HAUPT
HVAC-Final 2/15/2022 Approved SEAN HAUPT
MERV13>=Final 2/15/2022 Approved SEAN HAUPT
PLUMBING-Final 2/15/2022 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 2/15/2022 SGSOV Approved SEAN HAUPT
Smoke Detectors 2/15/2022 Approved SEAN HAUPT