7042 W 85TH ST 90045
Certificate Information: 7042 W 85TH ST 90045
- Application / Permit
- 20014-30000-05533
- Plan Check / Job No.
- B20WL05423
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to SFD
- Permit Issued
- Issued on 8/16/2021
- Issuing Office
- Current Status
- CofO Issued on 3/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2020 | KAVIAN REFAHI |
| Corrections Issued | 12/29/2020 | KAVIAN REFAHI |
| Building Plans Picked Up | 12/31/2020 | APPLICANT |
| Applicant returned to address corrections | 7/21/2021 | KHUONG TRUONG |
| Plan Check Approved | 8/11/2021 | SERGIO SILVA |
| Issued | 8/16/2021 | APPLICANT |
| CofO in Progress | 3/28/2023 | BOBBY KEY |
| Permit Finaled | 3/29/2023 | DANIEL ORRANTE |
| CofO Issued | 3/29/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/29/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZA Case | Cleared | 2/2/2021 | JASON CHAN |
| Sewer availability | Cleared | 2/23/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2021 | DINAH GARIN |
| Low Impact Development | Cleared | 7/14/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 7/14/2021 | DINAH GARIN |
Contact Information
| Architect | Sawyer, Robert Bernard; Lic. No.: C29302 | 8116 GONZAGA AVENUE LOS ANGELES, CA 90045 |
| Contractor | Sawyer Robert; Lic. No.: 817415-B | 8116 GONZAGA AVENUE LOS ANGELES, CA 90045 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/10/2021 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 9/27/2021 | Partial Approval | BRENDAN LOONEY |
| Green Building Rough | 9/27/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2021 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 3/9/2022 | Approved | BOBBY KEY |
| PLUMBING-Rough | 3/11/2022 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 3/14/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 3/31/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 4/7/2022 | Corrections Issued | BOBBY KEY |
| Deputy Wood Construction | 4/8/2022 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 4/25/2022 | Conditional Approval | BOBBY KEY |
| Green Building Rough | 4/25/2022 | Approved | BOBBY KEY |
| Insulation | 4/25/2022 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 5/9/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 5/9/2022 | Approved | BOBBY KEY |
| Insulation | 5/9/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 9/8/2022 | Approved | BOBBY KEY |
| Final | 9/8/2022 | Corrections Issued | BOBBY KEY |
| Green Building Final | 9/8/2022 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 9/12/2022 | Approved | BOBBY KEY |
| Final | 3/20/2023 | Corrections Issued | BOBBY KEY |
| Green Building Final | 3/20/2023 | Approved | BOBBY KEY |
| HVAC-Final | 3/20/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 3/20/2023 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 3/20/2023 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 3/20/2023 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 3/24/2023 | SGSOV Approved | BOBBY KEY |
| Final | 3/28/2023 | OK to Issue CofO | BOBBY KEY |