Interior structural remodel to (e) s.f.d. Balcony addition. Raise existing lower deck by 3 feet.
Permit Issued
Issued on 4/16/2021
Issuing Office
Current Status
Issued on 3/2/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/16/2020 APPLICANT
Assigned to Plan Check Engineer 12/23/2020 MARJAN SHENASI
Corrections Issued 12/26/2020 MARJAN SHENASI
Applicant returned to address corrections 2/7/2021 RICHARD GARCIA
Applicant returned to address corrections 2/25/2021 MARJAN SHENASI
Building Plans Picked Up 2/26/2021 APPLICANT
Applicant returned to address corrections 3/12/2021 RICHARD GARCIA
Applicant returned to address corrections 3/17/2021 RICHARD GARCIA
Plan Check Approved 4/6/2021 RICHARD GARCIA
Issued 4/16/2021 APPLICANT
CofO in Progress 2/24/2022 RAUL BARAJAS
CofO in Progress 2/24/2022 RAUL BARAJAS
No Progress 3/2/2022 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development Cleared 1/7/2021 ANDRES COVARRUBIAS
ZA Case Cleared 1/8/2021 LOUIS ORTEGA
ZA Case Cleared 1/8/2021 LOUIS ORTEGA
Eng Process Fee Ord 176,300 Cleared 1/20/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 1/20/2021 JEANIE LAM
Grading Pre-Inspection Cleared 2/25/2021 MARJAN SHENASI

Contact Information

Contractor Urbane Builders Inc; Lic. No.: 1046293-B 8619 RESEDA BLVD STE 304B      NORTHRIDGE, CA 91324
Engineer Pajuhesh,, Jamshid; Lic. No.: S1860 6824 LOUISE AVE      VAN NUYS, CA 91406

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 5/17/2021 No Access for Inspection ELMER BLAND
ELECTRICAL-Rough 5/24/2021 Partial Approval RAUL BARAJAS
HVAC-Rough 5/24/2021 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 5/24/2021 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 5/27/2021 Approved RAUL BARAJAS
HVAC-Rough 5/27/2021 Partial Approval RAUL BARAJAS
PLUMBING-Rough 5/27/2021 Partial Approval RAUL BARAJAS
Wood Frame 5/27/2021 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 6/1/2021 Approved RAUL BARAJAS
HVAC-Rough 6/1/2021 Approved RAUL BARAJAS
Insulation 6/1/2021 Approved RAUL BARAJAS
PLUMBING-Rough 6/1/2021 Approved RAUL BARAJAS
Structural Steel Frame 6/1/2021 Approved RAUL BARAJAS
Wood Frame 6/1/2021 Approved RAUL BARAJAS
Drywall Nailing 6/10/2021 Not Ready for Inspection RAUL BARAJAS
Interior/Exterior Lathing 6/10/2021 Not Ready for Inspection RAUL BARAJAS
Drywall Nailing 6/15/2021 Partial Approval RAUL BARAJAS
Interior/Exterior Lathing 6/15/2021 Not Ready for Inspection RAUL BARAJAS
Interior/Exterior Lathing 6/21/2021 Approved CHRISTOPHER DELLEFIELD
Shower Pan 6/21/2021 Approved CHRISTOPHER DELLEFIELD
Wood Frame 7/7/2021 Corrections Issued RAUL BARAJAS
Interior/Exterior Lathing 7/12/2021 Approved JUSTIN HAWLEY
HVAC-Rough 8/30/2021 Corrections Issued RAUL BARAJAS
Interior/Exterior Lathing 9/24/2021 Partial Approval SCOTT FINNILA
Interior/Exterior Lathing 9/27/2021 Approved RAUL BARAJAS
BUILDING-Rough-Frame 11/19/2021 Approved RAUL BARAJAS
Final 11/19/2021 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 11/19/2021 Not Ready for Inspection RAUL BARAJAS
Green Building Final 11/19/2021 Approved RAUL BARAJAS
Green Building Rough 11/19/2021 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 11/19/2021 SGSOV Approved RAUL BARAJAS
Smoke Detectors 11/19/2021 Not Ready for Inspection RAUL BARAJAS
Final 2/11/2022 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 2/11/2022 Approved RAUL BARAJAS
Smoke Detectors 2/11/2022 Approved RAUL BARAJAS
Final 2/18/2022 OK to Issue CofO RAUL BARAJAS