4509 N CEDROS AVE 91403

Certificate Information: 4509 N CEDROS AVE 91403

Application / Permit
20014-30000-05500
Plan Check / Job No.
B20WL05400
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-Story Addition/Remodel to (E) 2-Story S.F.D w/attached Garage
Permit Issued
Issued on 6/29/2021
Issuing Office
Current Status
CofO Issued on 7/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/11/2020 APPLICANT
Assigned to Plan Check Engineer 1/6/2021 DAVID CASTILLO
Corrections Issued 1/12/2021 DAVID CASTILLO
Quality Review Completed 1/22/2021 TARIK SAOUD
Building Plans Picked Up 2/26/2021 APPLICANT
Applicant returned to address corrections 5/11/2021 DAVID CASTILLO
Plan Check Approved 5/27/2021 DAVID CASTILLO
Issued 6/29/2021 APPLICANT
CofO in Progress 6/11/2025 JACK KARGODORIAN
Permit Finaled 7/8/2025 RUBEN SALAS
CofO Issued 7/8/2025 RUBEN SALAS
Permit Finaled 7/8/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/25/2021 ADRIAN CASTRO
Sewer availability Cleared 2/25/2021 ADRIAN CASTRO
Low Impact Development Cleared 4/14/2021 IDA MEISAMI-FARD
Roof/Waste drainage to street Cleared 4/27/2021 ABDULLAH SADOZAI

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Owner-Builder       ,
Engineer Thomas,, Ty Edward; Lic. No.: L9309 531 E TRENTON      ORANGE, CA 92867

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/6/2021 Partial Approval CHRISTOPHE COCHRAN
Underground Mechanical 7/6/2021 Approved CHRISTOPHE COCHRAN
Deputy Drilled-In Anchors 7/13/2021 Conditional Approval JAVIER RAMOS JR
Footing/Foundation/Slab 7/14/2021 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 8/18/2021 Corrections Issued ARAM AVEDISIAN
Deputy Wood Construction 8/19/2021 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 8/24/2021 Partial Approval CHARLES POWELL
Footing/Foundation/Slab 8/31/2021 Not Ready for Inspection CHARLES POWELL
Insulation 8/31/2021 Not Ready for Inspection CHARLES POWELL
Pre-Inspection 8/31/2021 Partial Approval AMY COLIN
Pre-Inspection 8/31/2021 Partial Inspection ALIZAH MAYAGOITIA
Special/Order Compliance 8/31/2021 Partial Inspection JUSTIN HAWLEY
Excavation/Setback/Form/Re-Bar 9/3/2021 Approved CHARLES POWELL
Insulation 9/3/2021 Partial Approval CHARLES POWELL
Gas Test 9/8/2021 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 9/8/2021 Corrections Issued CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 9/13/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Green Building Rough 9/13/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Rough 9/13/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Rough 9/13/2021 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 9/20/2021 Corrections Issued THOMAS FINNILA
HVAC-Rough 9/20/2021 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 9/22/2021 Approved MISAEL ESPARZA
HVAC-Rough 9/22/2021 Approved MISAEL ESPARZA
Interior/Exterior Lathing 10/1/2021 Not Ready for Inspection ALIZAH MAYAGOITIA
Shower Pan 10/1/2021 Corrections Issued ALIZAH MAYAGOITIA
Shower Pan 10/5/2021 Corrections Issued ASHLEY THOMPSON
BUILDING-Rough-Frame 10/12/2021 Corrections Issued MISAEL ESPARZA
Green Building Rough 10/12/2021 Not Ready for Inspection MISAEL ESPARZA
Shower Pan 10/13/2021 Corrections Issued JACK KARGODORIAN
Insulation 10/19/2021 Not Ready for Inspection JACK KARGODORIAN
Interior/Exterior Lathing 10/19/2021 Not Ready for Inspection JACK KARGODORIAN
Shower Pan 10/19/2021 Approved JACK KARGODORIAN
Insulation 10/22/2021 Partial Approval JACK KARGODORIAN
Interior/Exterior Lathing 10/25/2021 Partial Approval JACK KARGODORIAN
Interior/Exterior Lathing 10/28/2021 Partial Approval CHRISTOPHE COCHRAN
Drywall Nailing 11/4/2021 Approved JACK KARGODORIAN
Green Building Rough 11/4/2021 Approved JACK KARGODORIAN
ELECTRICAL-Rough 12/13/2021 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 12/28/2021 Approved JACK KARGODORIAN
Final 12/28/2021 Corrections Issued JACK KARGODORIAN
Footing/Foundation/Slab 12/28/2021 Approved JACK KARGODORIAN
Green Building Final 12/28/2021 Not Ready for Inspection JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 12/28/2021 SGSOV Not Ready JACK KARGODORIAN
Smoke Detectors 12/28/2021 Approved JACK KARGODORIAN
ELECTRICAL-Final 1/4/2022 Corrections Issued JACK KARGODORIAN
HVAC-Final 1/4/2022 Corrections Issued JACK KARGODORIAN
Final 1/7/2022 Corrections Issued JACK KARGODORIAN
Gas Test 1/7/2022 Approved JACK KARGODORIAN
Green Building Final 1/7/2022 Not Ready for Inspection JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 1/7/2022 SGSOV Approved JACK KARGODORIAN
ELECTRICAL-Final 1/11/2022 Corrections Issued JACK KARGODORIAN
HVAC-Final 1/11/2022 Approved JACK KARGODORIAN
PLUMBING-Final 1/11/2022 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Final 1/18/2022 Approved JACK KARGODORIAN
PLUMBING-Final 1/18/2022 Approved JACK KARGODORIAN
Service/Power Release 1/20/2022 Approved JACK KARGODORIAN
Final 3/10/2022 Corrections Issued JACK KARGODORIAN
Final 4/5/2022 Corrections Issued JACK KARGODORIAN
Green Building Final 4/5/2022 Approved JACK KARGODORIAN
Final 4/27/2022 Not Ready for Inspection JACK KARGODORIAN
Final 6/10/2025 OK to Issue CofO JACK KARGODORIAN