2027 S GLENDON AVE 90025

Certificate Information: 2027 S GLENDON AVE 90025

Application / Permit
20014-30000-05410
Plan Check / Job No.
B20WL05308
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND GARAGE CONVERSION INTO AN ADU PER LAMC 12.22a33(c) AND (d) AT REAR OF LOT.
Permit Issued
Issued on 4/29/2021
Issuing Office
Current Status
CofO Issued on 12/28/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/8/2020 APPLICANT
Assigned to Plan Check Engineer 12/10/2020 VLADIMIR ARUTYUNYAN
Corrections Issued 1/15/2021 VLADIMIR ARUTYUNYAN
Quality Review Completed 1/21/2021 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 1/28/2021 APPLICANT
Applicant returned to address corrections 4/21/2021 JAHANSHAH POURHASSAN
Plan Check Approved 4/27/2021 JAHANSHAH POURHASSAN
Issued 4/29/2021 APPLICANT
CofO in Progress 9/16/2021 OGANES TARAKHCHYAN
Permit Finaled 12/28/2021 KENNETH NAGLE
CofO Issued 12/28/2021 KENNETH NAGLE
Permit Finaled 12/28/2021 KENNETH NAGLE

Permit Application Clearance Information

Construction near power lines Cleared 3/4/2021 WALTER RAMIREZ
Hydrant and Access approval Cleared 3/4/2021 MATTHEW CRAIG
Address approval Cleared 3/18/2021 TRACY TATE
Roof/Waste drainage to street Cleared 3/18/2021 TRACY TATE
Sewer availability Cleared 3/18/2021 TRACY TATE
Eng Process Fee Ord 176,300 Cleared 3/19/2021 TRACY TATE
Low Impact Development Cleared 3/30/2021 MARTIN FRAGOSO
GPI Written Notices Cleared 4/21/2021 VLADIMIR ARUTYUNYAN
Grading Pre-Inspection Cleared 4/21/2021 VLADIMIR ARUTYUNYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22121 CLARENDON ST APT 340      WOODLAND HILLS, CA 91367

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/21/2021 Not Ready for Inspection OGANES TARAKHCHYAN
METHANE-Barrier 5/21/2021 Not Ready for Inspection OGANES TARAKHCHYAN
METHANE-Subgrade 5/21/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 5/24/2021 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 6/7/2021 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 6/17/2021 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 6/17/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Sewer 6/17/2021 Approved OGANES TARAKHCHYAN
HVAC-Rough 6/22/2021 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 6/24/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Rough 6/24/2021 Approved OGANES TARAKHCHYAN
METHANE-Rough 6/24/2021 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 6/24/2021 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 6/30/2021 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 7/2/2021 Approved AMY COLIN
Insulation 7/2/2021 Approved AMY COLIN
Interior/Exterior Lathing 7/2/2021 Not Ready for Inspection AMY COLIN
Shower Pan 7/2/2021 Approved AMY COLIN
Drywall Nailing 7/8/2021 Approved ADAM ESCOTO
Interior/Exterior Lathing 7/8/2021 Approved ADAM ESCOTO
Interior/Exterior Lathing 7/16/2021 Approved OGANES TARAKHCHYAN
Gas Test 8/30/2021 Approved OGANES TARAKHCHYAN
PLUMBING-Final 8/30/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Service/Power Release 8/30/2021 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Final 9/7/2021 Approved OGANES TARAKHCHYAN
HVAC-Final 9/7/2021 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Final 9/7/2021 Approved OGANES TARAKHCHYAN
Final 9/15/2021 OK to Issue CofO OGANES TARAKHCHYAN
Footing/Foundation/Slab 9/15/2021 Approved OGANES TARAKHCHYAN
Green Building Final 9/15/2021 Approved OGANES TARAKHCHYAN
HVAC-Final 9/15/2021 Approved OGANES TARAKHCHYAN
METHANE-Barrier 9/15/2021 Approved OGANES TARAKHCHYAN
METHANE-Subgrade 9/15/2021 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 9/15/2021 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 9/15/2021 Approved OGANES TARAKHCHYAN