1342 E PALMS BLVD 90291
Certificate Information: 1342 E PALMS BLVD 90291
- Application / Permit
- 20014-30000-05407
- Plan Check / Job No.
- B20WL05302
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD MASTER BDRM, BATHROOM & CLOSET. REMODEL (E) BATH
- Permit Issued
- Issued on 11/12/2021
- Issuing Office
- Current Status
- CofO Issued on 6/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2020 | RICHARD GARCIA |
| Corrections Issued | 12/20/2020 | RICHARD GARCIA |
| Applicant returned to address corrections | 7/29/2021 | MARJAN SHENASI |
| Applicant returned to address corrections | 8/10/2021 | KAVIAN REFAHI |
| Applicant returned to address corrections | 8/18/2021 | MANUEL GARCIA |
| Applicant returned to address corrections | 9/27/2021 | RICHARD GARCIA |
| Applicant returned to address corrections | 10/1/2021 | MANUEL GARCIA |
| Plan Check Approved | 11/4/2021 | MANUEL GARCIA |
| Issued | 11/12/2021 | APPLICANT |
| Building Plans Picked Up | 11/17/2021 | APPLICANT |
| CofO in Progress | 6/23/2023 | EVAN COOPER |
| Permit Finaled | 6/28/2023 | DANIEL ORRANTE |
| CofO Issued | 6/28/2023 | DANIEL ORRANTE |
| Permit Finaled | 6/28/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 2/5/2021 | PHILLIP MUNGUIA |
| Sewer availability | Cleared | 2/10/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2021 | DINAH GARIN |
| Specific Plan | Cleared | 3/31/2021 | RUBEN VASQUEZ |
| ZA Case | Cleared | 3/31/2021 | RUBEN VASQUEZ |
| ZI | Cleared | 3/31/2021 | RUBEN VASQUEZ |
| ZI | Cleared | 3/31/2021 | RUBEN VASQUEZ |
| ZI | Cleared | 3/31/2021 | RUBEN VASQUEZ |
| Low Impact Development | Cleared | 7/8/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 7/21/2021 | DINAH GARIN |
Contact Information
| Contractor | C B D Construction; Lic. No.: 552681-B | 26500 AGOURA ROAD BOX 848 CALABASAS, CA 91302 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/17/2021 | Partial Inspection | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 12/2/2021 | Partial Inspection | STEPHANIE SWANSON |
| Sewer | 12/2/2021 | Approved | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 12/6/2021 | Corrections Issued | DAVID FEILER |
| Deputy Drilled-In Anchors | 12/8/2021 | Approved | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 12/8/2021 | Approved | DAVID FEILER |
| Footing/Foundation/Slab | 12/8/2021 | Approved | DAVID FEILER |
| PLUMBING-Rough | 12/20/2021 | Partial Approval | DAVID FEILER |
| Wood Frame | 12/20/2021 | Corrections Issued | DAVID FEILER |
| BUILDING-Rough-Frame | 12/22/2021 | Partial Approval | ENRIQUE MIRELES |
| Wood Frame | 12/28/2021 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2022 | Corrections Issued | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2022 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 2/23/2022 | Not Ready for Inspection | RYAN SALAZAR |
| ELECTRICAL-Rough | 2/23/2022 | Corrections Issued | RYAN SALAZAR |
| Green Building Rough | 2/23/2022 | Not Ready for Inspection | RYAN SALAZAR |
| HVAC-Rough | 2/23/2022 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 2/23/2022 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 2/28/2022 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 2/28/2022 | Not Ready for Inspection | DAVID FEILER |
| Green Building Rough | 2/28/2022 | Corrections Issued | DAVID FEILER |
| Interior/Exterior Lathing | 2/28/2022 | Not Ready for Inspection | DAVID FEILER |
| Smoke Detectors | 2/28/2022 | Not Ready for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 3/3/2022 | Approved | DAVID FEILER |
| ELECTRICAL-Rough | 3/3/2022 | Approved | DAVID FEILER |
| Green Building Rough | 3/3/2022 | Approved | DAVID FEILER |
| Shower Pan | 3/3/2022 | Approved | DAVID FEILER |
| Insulation | 3/10/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 3/15/2022 | Partial Approval | JOHNNY MIRANDA |
| Drywall Nailing | 3/21/2022 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 3/21/2022 | Approved | DAVID FEILER |
| Underground Mechanical | 4/19/2022 | Partial Inspection | DAVID FEILER |
| Underground Mechanical | 4/28/2022 | Not Ready for Inspection | DAVID FEILER |
| Underground Mechanical | 5/13/2022 | Not Ready for Inspection | DAVID FEILER |
| Underground Mechanical | 5/17/2022 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 6/30/2022 | Corrections Issued | DAVID FEILER |
| Rough-Elec/Plmb/HVAC | 7/7/2022 | Partial Approval | DAVID FEILER |
| ELECTRICAL-Rough | 7/21/2022 | Approved | DAVID FEILER |
| HVAC-Rough | 7/21/2022 | Corrections Issued | DAVID FEILER |
| Insulation | 7/21/2022 | Approved | DAVID FEILER |
| Drywall Nailing | 8/1/2022 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 8/1/2022 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 8/22/2022 | Approved | DAVID FEILER |
| ELECTRICAL-Final | 6/22/2023 | Approved | EVAN COOPER |
| Final | 6/22/2023 | OK to Issue CofO | EVAN COOPER |
| Green Building Final | 6/22/2023 | Approved | EVAN COOPER |
| HVAC-Final | 6/22/2023 | Approved | EVAN COOPER |
| PLUMBING-Final | 6/22/2023 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 6/22/2023 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 6/22/2023 | Approved | EVAN COOPER |