7485 S DENROCK AVE 90045

Certificate Information: 7485 S DENROCK AVE 90045

Application / Permit
20014-30000-05401
Plan Check / Job No.
B20WL05292
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND INTERIOR REMODEL OF KITCHEN & BATHROOM TO (E) SFD
Permit Issued
Issued on 5/3/2021
Issuing Office
Current Status
CofO Issued on 3/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/7/2020 APPLICANT
Assigned to Plan Check Engineer 12/15/2020 JASON JANGADA
Corrections Issued 12/16/2020 JASON JANGADA
Building Plans Picked Up 12/22/2020 APPLICANT
Plan Check Approved 3/1/2021 MANUEL GARCIA
Issued 5/3/2021 APPLICANT
CofO in Progress 2/24/2022 BOBBY KEY
Permit Finaled 3/7/2022 DANIEL ORRANTE
CofO Issued 3/7/2022 DANIEL ORRANTE
Permit Finaled 3/7/2022 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/6/2021 DINAH GARIN
Sewer availability Cleared 1/6/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 1/7/2021 DINAH GARIN
Specific Plan Cleared 1/8/2021 PEDRO AYALA
Grading Pre-Inspection Cleared 3/1/2021 JASON JANGADA

Contact Information

Contractor Owner-Builder       ,
Engineer Sarkis,, Peter; Lic. No.: S5038 17981 SKY PARK CIR STE 0      IRVINE, CA 92614

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/5/2021 Conditional Approval BRENDAN LOONEY
Footing/Foundation/Slab 5/7/2021 Partial Approval MATT KELLERMAN
METHANE-Subgrade 5/7/2021 Approved MATT KELLERMAN
Wood Frame 6/1/2021 Partial Approval JOHNNY MIRANDA
Wood Frame 7/9/2021 Partial Approval BRENDAN LOONEY
Deputy Wood Construction 7/22/2021 Conditional Approval BRENDAN LOONEY
PLUMBING-Rough 7/23/2021 Approved BRENDAN LOONEY
Shower Pan 8/4/2021 Conditional Approval BRENDAN LOONEY
BUILDING-Rough-Frame 8/12/2021 Approved BRENDAN LOONEY
ELECTRICAL-Rough 8/12/2021 Approved BRENDAN LOONEY
Green Building Rough 8/12/2021 Not Ready for Inspection BRENDAN LOONEY
METHANE-Rough 8/12/2021 Approved BRENDAN LOONEY
Insulation 8/24/2021 Partial Approval BRENDAN LOONEY
Interior/Exterior Lathing 8/24/2021 Approved BRENDAN LOONEY
Drywall Nailing 8/27/2021 Approved BRENDAN LOONEY
Interior/Exterior Lathing 9/9/2021 Approved SHAVONNE ESPINOZA
Gas Test 12/29/2021 Approved BOBBY KEY
Green Building Final 1/19/2022 Approved BOBBY KEY
Insulation 1/19/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 1/26/2022 Approved BOBBY KEY
Final 1/26/2022 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 1/26/2022 Approved BOBBY KEY
Green Building Rough 1/26/2022 Approved BOBBY KEY
HVAC-Final 1/26/2022 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 1/26/2022 SGSOV Approved BOBBY KEY
ELECTRICAL-Final 2/10/2022 Approved BOBBY KEY
PLUMBING-Final 2/10/2022 Approved BOBBY KEY
Smoke Detectors 2/10/2022 Approved BOBBY KEY
Final 2/24/2022 OK to Issue CofO BOBBY KEY