7485 S DENROCK AVE 90045
Certificate Information: 7485 S DENROCK AVE 90045
- Application / Permit
- 20014-30000-05401
- Plan Check / Job No.
- B20WL05292
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND INTERIOR REMODEL OF KITCHEN & BATHROOM TO (E) SFD
- Permit Issued
- Issued on 5/3/2021
- Issuing Office
- Current Status
- CofO Issued on 3/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2020 | JASON JANGADA |
| Corrections Issued | 12/16/2020 | JASON JANGADA |
| Building Plans Picked Up | 12/22/2020 | APPLICANT |
| Plan Check Approved | 3/1/2021 | MANUEL GARCIA |
| Issued | 5/3/2021 | APPLICANT |
| CofO in Progress | 2/24/2022 | BOBBY KEY |
| Permit Finaled | 3/7/2022 | DANIEL ORRANTE |
| CofO Issued | 3/7/2022 | DANIEL ORRANTE |
| Permit Finaled | 3/7/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/6/2021 | DINAH GARIN |
| Sewer availability | Cleared | 1/6/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2021 | DINAH GARIN |
| Specific Plan | Cleared | 1/8/2021 | PEDRO AYALA |
| Grading Pre-Inspection | Cleared | 3/1/2021 | JASON JANGADA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sarkis,, Peter; Lic. No.: S5038 | 17981 SKY PARK CIR STE 0 IRVINE, CA 92614 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/5/2021 | Conditional Approval | BRENDAN LOONEY |
| Footing/Foundation/Slab | 5/7/2021 | Partial Approval | MATT KELLERMAN |
| METHANE-Subgrade | 5/7/2021 | Approved | MATT KELLERMAN |
| Wood Frame | 6/1/2021 | Partial Approval | JOHNNY MIRANDA |
| Wood Frame | 7/9/2021 | Partial Approval | BRENDAN LOONEY |
| Deputy Wood Construction | 7/22/2021 | Conditional Approval | BRENDAN LOONEY |
| PLUMBING-Rough | 7/23/2021 | Approved | BRENDAN LOONEY |
| Shower Pan | 8/4/2021 | Conditional Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 8/12/2021 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Rough | 8/12/2021 | Approved | BRENDAN LOONEY |
| Green Building Rough | 8/12/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| METHANE-Rough | 8/12/2021 | Approved | BRENDAN LOONEY |
| Insulation | 8/24/2021 | Partial Approval | BRENDAN LOONEY |
| Interior/Exterior Lathing | 8/24/2021 | Approved | BRENDAN LOONEY |
| Drywall Nailing | 8/27/2021 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 9/9/2021 | Approved | SHAVONNE ESPINOZA |
| Gas Test | 12/29/2021 | Approved | BOBBY KEY |
| Green Building Final | 1/19/2022 | Approved | BOBBY KEY |
| Insulation | 1/19/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 1/26/2022 | Approved | BOBBY KEY |
| Final | 1/26/2022 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 1/26/2022 | Approved | BOBBY KEY |
| Green Building Rough | 1/26/2022 | Approved | BOBBY KEY |
| HVAC-Final | 1/26/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 1/26/2022 | SGSOV Approved | BOBBY KEY |
| ELECTRICAL-Final | 2/10/2022 | Approved | BOBBY KEY |
| PLUMBING-Final | 2/10/2022 | Approved | BOBBY KEY |
| Smoke Detectors | 2/10/2022 | Approved | BOBBY KEY |
| Final | 2/24/2022 | OK to Issue CofO | BOBBY KEY |