3951 N CODY ROAD 91403
Certificate Information: 3951 N CODY ROAD 91403
- Application / Permit
- 20014-30000-05377
- Plan Check / Job No.
- B20WL05282
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD A CANTILEVER CANOPY TO THE FRONT SIDE OF (E) SFD (18'-6" x 6'-2")
- Permit Issued
- Issued on 5/3/2021
- Issuing Office
- Current Status
- CofO Issued on 8/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2021 | REZA HAGHIGHAT |
| Corrections Issued | 1/19/2021 | REZA HAGHIGHAT |
| Quality Review Completed | 1/21/2021 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 1/29/2021 | APPLICANT |
| Plan Check Approved | 3/26/2021 | REZA HAGHIGHAT |
| Issued | 5/3/2021 | APPLICANT |
| CofO in Progress | 7/15/2022 | JACK KARGODORIAN |
| Permit Finaled | 8/16/2022 | DANIEL ORRANTE |
| CofO Issued | 8/16/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/16/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 2/8/2021 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 2/8/2021 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 2/8/2021 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 2/8/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2021 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 2/8/2021 | ADRIAN CASTRO |
| Grading Pre-Inspection | Cleared | 3/26/2021 | REZA HAGHIGHAT |
Contact Information
| Architect | Asamoah,, B Kwesi; Lic. No.: C36558 | 850 ROSE AVENUE VENICE, CA 90291 |
| Architect | Guban,, Steven; Lic. No.: C33046 | 2608 BEACH AVENUE VENICE, CA 90291 |
| Contractor | Owner-Builder | , |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/15/2021 | Approved | CHARLES POWELL |
| BUILDING-Rough-Frame | 11/23/2021 | Not Ready for Inspection | MATT KELLERMAN |
| ELECTRICAL-Rough | 11/23/2021 | Not Ready for Inspection | MATT KELLERMAN |
| Green Building Rough | 11/23/2021 | Not Ready for Inspection | MATT KELLERMAN |
| ELECTRICAL-Rough | 12/6/2021 | Approved | JENNIFER RABUCHIN |
| Wood Frame | 12/6/2021 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 12/20/2021 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2021 | Approved | JACK KARGODORIAN |
| Green Building Rough | 12/20/2021 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 7/8/2022 | Approved | JACK KARGODORIAN |
| Final | 7/8/2022 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 7/8/2022 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 7/8/2022 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 7/8/2022 | Approved | JACK KARGODORIAN |
| Final | 7/15/2022 | OK to Issue CofO | JACK KARGODORIAN |