9029 W HARGIS ST 90034
Certificate Information: 9029 W HARGIS ST 90034
- Application / Permit
- 20014-30000-05259
- Plan Check / Job No.
- B20WL05229
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-Story addition w/attached Garage
- Permit Issued
- Issued on 3/25/2021
- Issuing Office
- Current Status
- CofO Issued on 2/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2020 | DAVID CASTILLO |
| Corrections Issued | 12/7/2020 | DAVID CASTILLO |
| Quality Review Completed | 12/17/2020 | TARIK SAOUD |
| Building Plans Picked Up | 12/17/2020 | APPLICANT |
| Plan Check Approved | 3/24/2021 | DAVID CASTILLO |
| Issued | 3/25/2021 | APPLICANT |
| CofO in Progress | 2/3/2022 | EVAN COOPER |
| Permit Finaled | 2/15/2022 | DANIEL ORRANTE |
| CofO Issued | 2/15/2022 | DANIEL ORRANTE |
| Permit Finaled | 2/15/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/17/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 12/17/2020 | RENZ SORIANO |
| Low Impact Development | Cleared | 3/10/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 3/17/2021 | THOMAS LANG |
| Demolition Pre-Inspection | Cleared | 3/24/2021 | DAVID CASTILLO |
| Grading Pre-Inspection | Cleared | 3/24/2021 | DAVID CASTILLO |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/3/2021 | Conditional Approval | EVAN COOPER |
| PLUMBING-Rough | 5/3/2021 | Conditional Approval | EVAN COOPER |
| Special/Order Compliance | 5/3/2021 | Corrections Issued | EVAN COOPER |
| Deputy Reinf. Concrete | 5/7/2021 | Conditional Approval | RYAN BARNES |
| Excavation/Setback/Form/Re-Bar | 5/7/2021 | Not Ready for Inspection | RYAN BARNES |
| Excavation/Setback/Form/Re-Bar | 6/8/2021 | Not Ready for Inspection | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 7/6/2021 | Conditional Approval | EVAN COOPER |
| Footing/Foundation/Slab | 7/6/2021 | Conditional Approval | EVAN COOPER |
| Footing/Foundation/Slab | 7/15/2021 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2021 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2021 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 9/3/2021 | Approved | EVAN COOPER |
| Shower Pan | 9/3/2021 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 9/14/2021 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 9/17/2021 | Partial Inspection | EVAN COOPER |
| HVAC-Rough | 9/22/2021 | Approved | EVAN COOPER |
| Green Building Rough | 9/28/2021 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 9/28/2021 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 10/5/2021 | Approved | EVAN COOPER |
| Green Building Rough | 10/5/2021 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 10/5/2021 | Partial Approval | EVAN COOPER |
| Verify Sprinkler Sign Off | 10/5/2021 | Approved | EVAN COOPER |
| Wood Frame | 10/8/2021 | Approved | EVAN COOPER |
| Insulation | 10/15/2021 | Conditional Approval | EVAN COOPER |
| Drywall Nailing | 10/22/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 10/27/2021 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 12/27/2021 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 12/27/2021 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 12/29/2021 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 12/30/2021 | Approved | EVAN COOPER |
| PLUMBING-Final | 1/4/2022 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Final | 1/6/2022 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Final | 1/7/2022 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Final | 1/11/2022 | Approved | EVAN COOPER |
| Service/Power Release | 1/11/2022 | Not Ready for Inspection | EVAN COOPER |
| Gas Test | 1/13/2022 | Approved | EVAN COOPER |
| PLUMBING-Final | 1/13/2022 | Approved | EVAN COOPER |
| Service/Power Release | 1/25/2022 | Approved | EVAN COOPER |
| Drywall Nailing | 1/26/2022 | Approved | EVAN COOPER |
| Final | 1/26/2022 | Conditional Approval | EVAN COOPER |
| Green Building Final | 1/26/2022 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 1/26/2022 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 1/26/2022 | Approved | EVAN COOPER |
| Special/Order Compliance | 1/27/2022 | Corrections Issued | EVAN COOPER |
| Final | 2/3/2022 | OK to Issue CofO | EVAN COOPER |
| Posting Pre-Inspection | 2/3/2022 | Approved | EVAN COOPER |
| Special/Order Compliance | 2/3/2022 | Approved | EVAN COOPER |
| Verify Rec and Parks Fee Memo | 2/3/2022 | Approved | EVAN COOPER |