9029 W HARGIS ST 90034

Certificate Information: 9029 W HARGIS ST 90034

Application / Permit
20014-30000-05259
Plan Check / Job No.
B20WL05229
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-Story addition w/attached Garage
Permit Issued
Issued on 3/25/2021
Issuing Office
Current Status
CofO Issued on 2/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/30/2020 APPLICANT
Assigned to Plan Check Engineer 12/2/2020 DAVID CASTILLO
Corrections Issued 12/7/2020 DAVID CASTILLO
Quality Review Completed 12/17/2020 TARIK SAOUD
Building Plans Picked Up 12/17/2020 APPLICANT
Plan Check Approved 3/24/2021 DAVID CASTILLO
Issued 3/25/2021 APPLICANT
CofO in Progress 2/3/2022 EVAN COOPER
Permit Finaled 2/15/2022 DANIEL ORRANTE
CofO Issued 2/15/2022 DANIEL ORRANTE
Permit Finaled 2/15/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/17/2020 RENZ SORIANO
Sewer availability Cleared 12/17/2020 RENZ SORIANO
Low Impact Development Cleared 3/10/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 3/17/2021 THOMAS LANG
Demolition Pre-Inspection Cleared 3/24/2021 DAVID CASTILLO
Grading Pre-Inspection Cleared 3/24/2021 DAVID CASTILLO

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/3/2021 Conditional Approval EVAN COOPER
PLUMBING-Rough 5/3/2021 Conditional Approval EVAN COOPER
Special/Order Compliance 5/3/2021 Corrections Issued EVAN COOPER
Deputy Reinf. Concrete 5/7/2021 Conditional Approval RYAN BARNES
Excavation/Setback/Form/Re-Bar 5/7/2021 Not Ready for Inspection RYAN BARNES
Excavation/Setback/Form/Re-Bar 6/8/2021 Not Ready for Inspection EVAN COOPER
Excavation/Setback/Form/Re-Bar 7/6/2021 Conditional Approval EVAN COOPER
Footing/Foundation/Slab 7/6/2021 Conditional Approval EVAN COOPER
Footing/Foundation/Slab 7/15/2021 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 7/27/2021 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 8/13/2021 Partial Approval EVAN COOPER
PLUMBING-Rough 9/3/2021 Approved EVAN COOPER
Shower Pan 9/3/2021 Approved EVAN COOPER
ELECTRICAL-Rough 9/14/2021 Approved EVAN COOPER
Interior/Exterior Lathing 9/17/2021 Partial Inspection EVAN COOPER
HVAC-Rough 9/22/2021 Approved EVAN COOPER
Green Building Rough 9/28/2021 Approved EVAN COOPER
Interior/Exterior Lathing 9/28/2021 Approved EVAN COOPER
BUILDING-Rough-Frame 10/5/2021 Approved EVAN COOPER
Green Building Rough 10/5/2021 Approved EVAN COOPER
Interior/Exterior Lathing 10/5/2021 Partial Approval EVAN COOPER
Verify Sprinkler Sign Off 10/5/2021 Approved EVAN COOPER
Wood Frame 10/8/2021 Approved EVAN COOPER
Insulation 10/15/2021 Conditional Approval EVAN COOPER
Drywall Nailing 10/22/2021 Partial Approval OGANES TARAKHCHYAN
Interior/Exterior Lathing 10/27/2021 Approved EVAN COOPER
ELECTRICAL-Final 12/27/2021 Corrections Issued EVAN COOPER
HVAC-Final 12/27/2021 Corrections Issued EVAN COOPER
HVAC-Final 12/29/2021 Corrections Issued EVAN COOPER
HVAC-Final 12/30/2021 Approved EVAN COOPER
PLUMBING-Final 1/4/2022 Not Ready for Inspection EVAN COOPER
PLUMBING-Final 1/6/2022 Corrections Issued EVAN COOPER
ELECTRICAL-Final 1/7/2022 Corrections Issued EVAN COOPER
ELECTRICAL-Final 1/11/2022 Approved EVAN COOPER
Service/Power Release 1/11/2022 Not Ready for Inspection EVAN COOPER
Gas Test 1/13/2022 Approved EVAN COOPER
PLUMBING-Final 1/13/2022 Approved EVAN COOPER
Service/Power Release 1/25/2022 Approved EVAN COOPER
Drywall Nailing 1/26/2022 Approved EVAN COOPER
Final 1/26/2022 Conditional Approval EVAN COOPER
Green Building Final 1/26/2022 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 1/26/2022 SGSOV Approved EVAN COOPER
Smoke Detectors 1/26/2022 Approved EVAN COOPER
Special/Order Compliance 1/27/2022 Corrections Issued EVAN COOPER
Final 2/3/2022 OK to Issue CofO EVAN COOPER
Posting Pre-Inspection 2/3/2022 Approved EVAN COOPER
Special/Order Compliance 2/3/2022 Approved EVAN COOPER
Verify Rec and Parks Fee Memo 2/3/2022 Approved EVAN COOPER