8212 S WINSFORD AVE 90045
Certificate Information: 8212 S WINSFORD AVE 90045
- Application / Permit
- 20014-30000-05217
- Plan Check / Job No.
- B20WL05180
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) Trellis, Ground Floor Addition, Roof Replacement and Remodel to (E) 1-Story S.F.D w/Attached Garage
- Permit Issued
- Issued on 1/3/2022
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 8/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2021 | DAVID CASTILLO |
| Corrections Issued | 1/12/2021 | DAVID CASTILLO |
| Quality Review Completed | 1/22/2021 | TARIK SAOUD |
| Building Plans Picked Up | 1/28/2021 | APPLICANT |
| Applicant returned to address corrections | 12/7/2021 | DAVID CASTILLO |
| Plan Check Approved | 12/23/2021 | DAVID CASTILLO |
| Issued | 1/3/2022 | APPLICANT |
| CofO in Progress | 8/4/2023 | BOBBY KEY |
| Permit Finaled | 8/15/2023 | DANIEL ORRANTE |
| CofO Issued | 8/15/2023 | DANIEL ORRANTE |
| Permit Finaled | 8/15/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2021 | RAYMOND MUGAMBWA |
| Roof/Waste drainage to street | Cleared | 3/16/2021 | RAYMOND MUGAMBWA |
| Sewer availability | Cleared | 3/16/2021 | RAYMOND MUGAMBWA |
| Grading Pre-Inspection | Cleared | 5/3/2021 | KIRK LINKLATER |
| Construction within easement | Cleared | 6/30/2021 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/24/2022 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2022 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 11/3/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2022 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 2/14/2023 | Corrections Issued | BOBBY KEY |
| Green Building Rough | 2/14/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 2/14/2023 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 2/14/2023 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 2/14/2023 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 2/21/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 2/21/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 2/21/2023 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 2/21/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 2/27/2023 | Approved | JESUS RODRIGUEZ |
| Insulation | 2/27/2023 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 3/13/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 4/5/2023 | Partial Approval | BOBBY KEY |
| Shower Pan | 4/5/2023 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 4/10/2023 | Approved | BOBBY KEY |
| Shower Pan | 4/10/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 7/27/2023 | Corrections Issued | BOBBY KEY |
| Final | 7/27/2023 | Corrections Issued | BOBBY KEY |
| Green Building Final | 7/27/2023 | Approved | BOBBY KEY |
| HVAC-Final | 7/27/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 7/27/2023 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 7/27/2023 | SGSOV Not Ready | BOBBY KEY |
| Service/Power Release | 7/27/2023 | Not Ready for Inspection | BOBBY KEY |
| Smoke Detectors | 7/27/2023 | Approved | BOBBY KEY |
| Special/Order Compliance | 7/31/2023 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Final | 8/4/2023 | Approved | BOBBY KEY |
| Final | 8/4/2023 | OK to Issue CofO | BOBBY KEY |
| HVAC-Final | 8/4/2023 | Approved | BOBBY KEY |
| PLUMBING-Final | 8/4/2023 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 8/4/2023 | SGSOV Approved | BOBBY KEY |
| Service/Power Release | 8/4/2023 | Approved | BOBBY KEY |