11714 W CRESCENDA ST 90049
Certificate Information: 11714 W CRESCENDA ST 90049
- Application / Permit
- 20014-30000-05214
- Plan Check / Job No.
- B20WL05172
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel and ground floor addition to existing SFD.
- Permit Issued
- Issued on 10/14/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2021 | TARIK SAOUD |
| Corrections Issued | 3/31/2021 | TARIK SAOUD |
| Quality Review Completed | 4/9/2021 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 6/6/2022 | TARIK SAOUD |
| Applicant returned to address corrections | 8/11/2022 | TARIK SAOUD |
| Applicant returned to address corrections | 9/8/2022 | TARIK SAOUD |
| Applicant returned to address corrections | 9/21/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 9/22/2022 | APPLICANT |
| Applicant returned to address corrections | 10/5/2022 | CHIHARU SUZUKI |
| Plan Check Approved | 10/7/2022 | CHIHARU SUZUKI |
| Issued | 10/14/2022 | APPLICANT |
| CofO in Progress | 2/19/2025 | CARLOS MATAMOROS |
| CofO Issued | 2/21/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/21/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 1/11/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 1/25/2022 | NIKTA MOUSAVI |
| Eng Process Fee Ord 176,300 | Cleared | 3/17/2022 | NIKTA MOUSAVI |
| Sewer availability | Cleared | 3/17/2022 | NIKTA MOUSAVI |
| Grading Pre-Inspection | Cleared | 6/6/2022 | TARIK SAOUD |
Contact Information
| Architect | Jewell,, Ward E; Lic. No.: C26187 | 7825 HENEFER AVE LOS ANGELES, CA 90045 |
| Contractor | Premier General Contractors Inc; Lic. No.: 638046-B | 1131 N GRANADA AVE ALHAMBRA, CA 91801 |
| Engineer | Yamini,, Soly; Lic. No.: C33719 | 540 WARNER AVE LOS ANGELES, CA 90024 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/15/2023 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 2/15/2023 | Partial Approval | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 3/8/2023 | Partial Approval | CARLOS MATAMOROS |
| Green Building Rough | 3/8/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Wood Frame | 3/10/2023 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 5/3/2023 | Corrections Issued | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 5/12/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 5/23/2023 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2023 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 5/23/2023 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2023 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 6/30/2023 | Partial Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2023 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2023 | Approved | CARLOS MATAMOROS |
| Deputy Wood Construction | 10/18/2023 | Conditional Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 11/21/2023 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 11/30/2023 | Approved | CARLOS MATAMOROS |
| Special/Order Compliance | 12/1/2023 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 12/19/2023 | Corrections Issued | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 12/29/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| Gas Test | 1/18/2024 | Approved | CARLOS MATAMOROS |
| Shower Pan | 1/24/2024 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 1/31/2024 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 2/14/2024 | Corrections Issued | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 2/20/2024 | Approved | CARLOS MATAMOROS |
| Gas Test | 11/15/2024 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 1/28/2025 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 1/28/2025 | Corrections Issued | CARLOS MATAMOROS |
| Final | 1/28/2025 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Final | 1/28/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Rough | 1/28/2025 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 1/28/2025 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Final | 1/28/2025 | Corrections Issued | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 1/28/2025 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 1/28/2025 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Final | 2/11/2025 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Final | 2/11/2025 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 2/11/2025 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 2/11/2025 | Approved | CARLOS MATAMOROS |
| Smoke Detectors | 2/11/2025 | Approved | CARLOS MATAMOROS |
| Special/Order Compliance | 2/11/2025 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Final | 2/13/2025 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 2/18/2025 | Approved | CARLOS MATAMOROS |
| Final | 2/18/2025 | OK to Issue CofO | CARLOS MATAMOROS |
| Service/Power Release | 4/7/2025 | Approved | CARLOS MATAMOROS |