747 N LATIMER ROAD 90402
Certificate Information: 747 N LATIMER ROAD 90402
- Application / Permit
- 20014-30000-05211
- Plan Check / Job No.
- B20WL05163
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ALTERATION AND GROUND FLOOR ADDITION TO EXISTING 2-STORY SFD.
- Permit Issued
- Issued on 10/14/2021
- Issuing Office
- Current Status
- CofO Issued on 6/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2020 | TARIK SAOUD |
| Corrections Issued | 12/9/2020 | TARIK SAOUD |
| Quality Review Completed | 12/17/2020 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 12/18/2020 | APPLICANT |
| Applicant returned to address corrections | 3/25/2021 | TARIK SAOUD |
| Plan Check Approved | 8/12/2021 | TARIK SAOUD |
| Issued | 10/14/2021 | APPLICANT |
| CofO in Progress | 6/12/2025 | MEL KHACHATOURIAN |
| Permit Finaled | 6/26/2025 | RICHARD STEINBACH |
| CofO Issued | 6/26/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/26/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 2/9/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 2/9/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 2/9/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 2/9/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 2/9/2021 | DINAH GARIN |
| Sewer availability | Cleared | 2/9/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/23/2021 | DINAH GARIN |
| ZA Case | Cleared | 3/17/2021 | ANACANY HURTADO |
| ZA Case | Cleared | 3/17/2021 | ANACANY HURTADO |
| Miscellaneous | Cleared | 4/15/2021 | JENSON LEE |
| Hydrant and Access approval | Cleared | 5/11/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 6/24/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 7/29/2021 | MAHELET GEBEYHU |
| Watercourse | Cleared | 7/29/2021 | MAHELET GEBEYHU |
| Grading Pre-Inspection | Cleared | 8/12/2021 | TARIK SAOUD |
Contact Information
| Architect | Yudell,, Robert Jonathan; Lic. No.: C15469 | 933 PICO BLVD SANTA MONICA, CA 90405 |
| Contractor | Garrett Oliver Construction Inc; Lic. No.: 671397-B | 881 WARREN AVENUE VENICE, CA 90291 |
| Engineer | Bornand,, Christophe N; Lic. No.: C80596 | 3582 VETERAN AVE LOS ANGELES, CA 90034 |
| Engineer | Hollingsworth,, Robert Alan; Lic. No.: GE2022 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Polon,, Gordon Leonard; Lic. No.: C28564 | 709 19TH STREET SANTA MONICA, CA 90402 |
| Geologist | Hollingsworth,, Robert Alan; Lic. No.: EG1265 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/10/2022 | Corrections Issued | JOHN KIDWELL |
| Pre-Inspection | 1/14/2022 | Partial Inspection | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 1/21/2022 | Partial Approval | JOHN KIDWELL |
| Deputy Grading | 1/26/2022 | Partial Approval | JOHN KIDWELL |
| Deputy Reinf. Concrete | 1/26/2022 | Partial Approval | JOHN KIDWELL |
| Deputy Grading | 1/28/2022 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 2/10/2022 | Partial Approval | ANDREW NAVE |
| Deputy Steel/Welding | 2/16/2022 | Partial Approval | JOHN KIDWELL |
| FLOOD-Elevation Certificate | 2/23/2022 | Approved | MICHAEL PELHAM |
| Footing/Foundation/Slab | 2/23/2022 | Partial Approval | MICHAEL PELHAM |
| Sewer | 3/17/2022 | Partial Inspection | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 3/21/2022 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 4/6/2022 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 4/6/2022 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 4/12/2022 | Partial Approval | JOHN KIDWELL |
| Deputy Drilled-In Anchors | 4/26/2022 | Approved | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 4/26/2022 | Approved | MICHAEL PELHAM |
| Footing/Foundation/Slab | 4/27/2022 | Partial Approval | JOHN KIDWELL |
| Deputy Reinf. Concrete | 4/28/2022 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 5/9/2022 | Approved | JOHN KIDWELL |
| Deputy Drilled-In Anchors | 5/10/2022 | Partial Approval | JOHN KIDWELL |
| Reinforced Concrete Frame | 5/12/2022 | Partial Inspection | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2022 | Partial Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 6/2/2022 | Partial Approval | ANDREW NAVE |
| PLUMBING-Rough | 6/9/2022 | Partial Approval | JOHN KIDWELL |
| HVAC-Rough | 6/30/2022 | Partial Inspection | ANDREW NAVE |
| Pre-Inspection | 7/6/2022 | Partial Inspection | JOHN KIDWELL |
| Sewer | 8/25/2022 | Corrections Issued | KEVIN SARGSYAN |
| Sewer | 8/26/2022 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 8/29/2022 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 8/31/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Wood Frame | 8/31/2022 | Partial Approval | KEVIN SARGSYAN |
| Pre-Inspection | 9/14/2022 | Partial Inspection | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 9/28/2022 | SGSOV Not Ready | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2022 | Partial Approval | KEVIN SARGSYAN |
| Pre-Inspection | 11/16/2022 | Partial Inspection | KEVIN SARGSYAN |
| Pre-Inspection | 11/22/2022 | Partial Inspection | KENNETH NAGLE |
| ELECTRICAL-Rough | 1/13/2023 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 2/3/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Underground Mechanical | 2/21/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Underground Mechanical | 3/6/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Underground Mechanical | 3/24/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Drywall Nailing | 5/4/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 5/4/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 5/15/2023 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Insulation | 7/10/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Pre-Inspection | 7/13/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 8/3/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2023 | Approved | OGANES TARAKHCHYAN |
| Pre-Inspection | 8/22/2023 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 9/6/2023 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 10/6/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Green Building Rough | 10/24/2023 | Partial Inspection | KENNETH NAGLE |
| HVAC-Rough | 11/8/2023 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 11/15/2023 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 11/15/2023 | Approved | ARAM AVEDISIAN |
| Insulation | 11/20/2023 | Approved | ARAM AVEDISIAN |
| Special/Order Compliance | 12/7/2023 | Corrections Issued | ARAM AVEDISIAN |
| Drywall Nailing | 1/8/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Drywall Nailing | 1/23/2024 | Approved | JESUS PINEDA |
| Underground Mechanical | 1/23/2024 | Partial Approval | JESUS PINEDA |
| HVAC-Rough | 1/30/2024 | Partial Approval | EVAN COOPER |
| Shower Pan | 3/4/2024 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 3/18/2024 | Partial Approval | ARAM AVEDISIAN |
| Underground Mechanical | 7/1/2024 | Partial Approval | ARAM AVEDISIAN |
| Gas Test | 8/6/2024 | Not Ready for Inspection | KENNETH NAGLE |
| Gas Test | 8/8/2024 | Approved | KENNETH NAGLE |
| Sewer | 8/13/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Final | 11/12/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 11/12/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 12/10/2024 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 12/10/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Service/Power Release | 2/3/2025 | Approved | JESUS RODRIGUEZ |
| Final | 2/13/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 2/13/2025 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 2/13/2025 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 2/13/2025 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 2/13/2025 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 6/11/2025 | Approved | MEL KHACHATOURIAN |
| Final | 6/11/2025 | OK to Issue CofO | MEL KHACHATOURIAN |