131 S SALTAIR AVE 90049

Certificate Information: 131 S SALTAIR AVE 90049

Application / Permit
20014-30000-05136
Plan Check / Job No.
B20WL05059
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
remodel of an existing 1627 sf single family home with attached garage. addition of 1108 sf including a second story. addition of an attached open air trellis
Permit Issued
Issued on 4/29/2021
Issuing Office
Valley
Current Status
CofO Issued on 3/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/20/2020 APPLICANT
Assigned to Plan Check Engineer 12/16/2020 FELIPE HERNANDEZ
Corrections Issued 12/22/2020 FELIPE HERNANDEZ
Quality Review Completed 12/29/2020 TARIK SAOUD
Applicant returned to address corrections 2/23/2021 FELIPE HERNANDEZ
Applicant returned to address corrections 3/5/2021 FELIPE HERNANDEZ
Building Plans Picked Up 3/5/2021 APPLICANT
Applicant returned to address corrections 3/17/2021 FELIPE HERNANDEZ
Applicant returned to address corrections 4/1/2021 FELIPE HERNANDEZ
Plan Check Approved 4/7/2021 FELIPE HERNANDEZ
Issued 4/29/2021 APPLICANT
CofO in Progress 12/14/2022 KEVIN SARGSYAN
No Progress 12/28/2022 KENNETH NAGLE
CofO in Progress 3/16/2023 KENNETH NAGLE
Permit Finaled 3/17/2023 DANIEL ORRANTE
CofO Issued 3/17/2023 DANIEL ORRANTE
Permit Finaled 3/17/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/20/2021 DINAH GARIN
Sewer availability Cleared 1/20/2021 DINAH GARIN
Hydrant and Access approval Cleared 2/24/2021 MATTHEW CRAIG
Low Impact Development Cleared 3/5/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 3/9/2021 DINAH GARIN
Specific Plan Cleared 3/10/2021 PETE EYRE
Grading Pre-Inspection Cleared 4/7/2021 FELIPE HERNANDEZ

Contact Information

Architect Shepphird,, William Reynolds; Lic. No.: C28818 P O BOX 8446      CALABASAS, CA 91372
Contractor Amerbuild Inc; Lic. No.: 1024554-B 22108 VANOWEN STREET      WOODLAND HILLS, CA 91303
Engineer Shepphird,, William Reynolds; Lic. No.: C59229 PO BOX 8446      CALABASAS, CA 91372

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/12/2021 Conditional Approval JOHN KIDWELL
Deputy Reinf. Concrete 5/13/2021 Corrections Issued JOHN KIDWELL
Deputy Reinf. Concrete 5/14/2021 Corrections Issued JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 5/18/2021 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 5/21/2021 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 9/9/2021 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 9/9/2021 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 10/1/2021 Approved JOHN KIDWELL
HVAC-Rough 10/1/2021 Approved JOHN KIDWELL
BUILDING-Rough-Frame 10/13/2021 Partial Approval JOHN KIDWELL
Green Building Rough 10/13/2021 Approved JOHN KIDWELL
Shower Pan 11/17/2021 Approved DEANDRE HOFFMAN
Interior/Exterior Lathing 12/13/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 12/23/2021 Partial Approval JUAN VALENZUELA
Insulation 1/26/2022 Approved JOHN KIDWELL
Drywall Nailing 2/8/2022 Approved JOHN KIDWELL
BUILDING-Rough-Frame 8/18/2022 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Final 8/18/2022 Not Ready for Inspection KEVIN SARGSYAN
Final 8/18/2022 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 8/18/2022 Not Ready for Inspection KEVIN SARGSYAN
Green Building Final 8/18/2022 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Final 8/18/2022 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Final 8/18/2022 Not Ready for Inspection KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 8/18/2022 SGSOV Approved KEVIN SARGSYAN
Smoke Detectors 8/18/2022 Not Ready for Inspection KEVIN SARGSYAN
Gas Test 8/22/2022 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 9/14/2022 Approved KEVIN SARGSYAN
ELECTRICAL-Final 10/7/2022 Approved ANDREW NAVE
Service/Power Release 10/7/2022 Approved ANDREW NAVE
HVAC-Final 10/12/2022 Corrections Issued ANDREW NAVE
PLUMBING-Final 10/12/2022 Corrections Issued ANDREW NAVE
BUILDING-Rough-Frame 11/1/2022 Approved KEVIN SARGSYAN
Final 11/1/2022 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 11/1/2022 Approved KEVIN SARGSYAN
Green Building Final 11/1/2022 Approved KEVIN SARGSYAN
HVAC-Final 11/1/2022 Approved KEVIN SARGSYAN
PLUMBING-Final 11/1/2022 Approved KEVIN SARGSYAN
Smoke Detectors 11/1/2022 Approved KEVIN SARGSYAN
Final 12/14/2022 OK to Issue CofO KEVIN SARGSYAN