2400 S HALM AVE 90034

Certificate Information: 2400 S HALM AVE 90034

Application / Permit
20014-30000-05126
Plan Check / Job No.
B20WL05052
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Rear addition and remodel (E) single family dwelling.
Permit Issued
Issued on 3/3/2021
Issuing Office
Current Status
CofO Issued on 4/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/20/2020 APPLICANT
Assigned to Plan Check Engineer 11/23/2020 MARJAN SHENASI
Corrections Issued 11/27/2020 MARJAN SHENASI
Applicant returned to address corrections 1/7/2021 RICHARD GARCIA
Plan Check Approved 2/15/2021 MARJAN SHENASI
Issued 3/3/2021 APPLICANT
Building Plans Picked Up 3/5/2021 APPLICANT
CofO in Progress 2/3/2022 GERMAN RODRIGUEZ MENDOZA
Permit Finaled 4/19/2022 DANIEL ORRANTE
CofO Issued 4/19/2022 DANIEL ORRANTE
Permit Finaled 4/19/2022 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/2/2021 JEANIE LAM
Sewer availability Cleared 2/2/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 2/8/2021 JEANIE LAM

Contact Information

Architect Williams,, Jann Catherine; Lic. No.: C22755 10551 LINDBROOK DRIVE      LOS ANGELES, CA 90024
Contractor Elemental Design Inc; Lic. No.: 897423-B 3038 HILLCREST DRIVE      LOS ANGELES, CA 900164101
Engineer Shoraka,, Khojasteh Farhang; Lic. No.: C33555 1423 S BEVERLY GLEN UNIT A      LOS ANGELES, CA 90024

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/16/2021 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 3/16/2021 Conditional Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 3/19/2021 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 3/19/2021 Approved EVAN COOPER
BUILDING-Rough-Frame 3/25/2021 Partial Approval JOHNNY MIRANDA
Green Building Rough 3/25/2021 Not Ready for Inspection JOHNNY MIRANDA
MERV13>=Rough 3/25/2021 Not Ready for Inspection JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 3/26/2021 Partial Approval EVAN COOPER
Insulation 3/26/2021 Partial Approval EVAN COOPER
ELECTRICAL-Rough 4/9/2021 Not Ready for Inspection EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 4/9/2021 Partial Inspection EVAN COOPER
PLUMBING-Rough 4/9/2021 Not Ready for Inspection EVAN COOPER
BUILDING-Rough-Frame 4/12/2021 Partial Approval EVAN COOPER
ELECTRICAL-Rough 4/12/2021 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 4/12/2021 Partial Approval EVAN COOPER
Green Building Rough 4/12/2021 Not Ready for Inspection EVAN COOPER
MERV13>=Rough 4/12/2021 Approved EVAN COOPER
PLUMBING-Rough 4/12/2021 Approved EVAN COOPER
Wood Frame 4/12/2021 Partial Approval EVAN COOPER
HVAC-Rough 4/27/2021 Partial Approval EVAN COOPER
Insulation 5/6/2021 Approved EVAN COOPER
Interior/Exterior Lathing 5/6/2021 Approved EVAN COOPER
Shower Pan 5/6/2021 Approved EVAN COOPER
Wood Frame 5/20/2021 Conditional Approval EVAN COOPER
Drywall Nailing 6/8/2021 Approved ADAM ESCOTO
Interior/Exterior Lathing 6/21/2021 Approved AMY COLIN
BUILDING-Rough-Frame 11/30/2021 Approved EVAN COOPER
ELECTRICAL-Final 11/30/2021 Approved EVAN COOPER
Final 11/30/2021 Corrections Issued EVAN COOPER
Green Building Final 11/30/2021 Not Ready for Inspection EVAN COOPER
Green Building Rough 11/30/2021 Approved EVAN COOPER
HVAC-Final 11/30/2021 Approved EVAN COOPER
MERV13>=Final 11/30/2021 Approved EVAN COOPER
PLUMBING-Final 11/30/2021 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 11/30/2021 SGSOV Not Ready EVAN COOPER
Smoke Detectors 11/30/2021 Not Ready for Inspection EVAN COOPER
Final 2/2/2022 OK to Issue CofO GERMAN RODRIGUEZ MENDOZA
Green Building Final 2/2/2022 Approved GERMAN RODRIGUEZ MENDOZA
SGSOV-Seismic Gas S/O Valve 2/2/2022 SGSOV Approved GERMAN RODRIGUEZ MENDOZA
Smoke Detectors 2/2/2022 Approved GERMAN RODRIGUEZ MENDOZA