3220 S MIDVALE AVE 90034

Certificate Information: 3220 S MIDVALE AVE 90034

Application / Permit
20014-30000-05112
Plan Check / Job No.
B20WL05034
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior Remodel of (E) 1-Story S.F.D & (N) Open Deck (9'-1" x 25'-11 3/4")
Permit Issued
Issued on 9/10/2021
Issuing Office
Current Status
Permit Finaled on 12/8/2022

Permit Application Status History

Submitted 11/21/2020 APPLICANT
Assigned to Plan Check Engineer 12/16/2020 DAVID CASTILLO
Corrections Issued 12/21/2020 DAVID CASTILLO
Quality Review Completed 12/28/2020 TARIK SAOUD
Building Plans Picked Up 1/4/2021 APPLICANT
Applicant returned to address corrections 5/5/2021 DAVID CASTILLO
Applicant returned to address corrections 6/8/2021 DAVID CASTILLO
Applicant returned to address corrections 7/13/2021 DAVID CASTILLO
Plan Check Approved 7/16/2021 DAVID CASTILLO
Issued 9/10/2021 APPLICANT
Permit Finaled 12/7/2022 JOHNNY MIRANDA

Permit Application Clearance Information

Sewer availability Cleared 2/9/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 2/10/2021 DINAH GARIN
Roof/Waste drainage to street Cleared 5/17/2021 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 5/18/2021 KIRK LINKLATER

Contact Information

Contractor Navarro Construction; Lic. No.: 1042757-B 22412 MARBELLA AVE      CARSON, CA 90745
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/5/2021 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 11/30/2021 Partial Approval JOHNNY MIRANDA
Wood Frame 11/30/2021 Partial Approval JOHNNY MIRANDA
Interior/Exterior Lathing 12/21/2021 Partial Approval JOHNNY MIRANDA
Special/Order Compliance 12/21/2021 Corrections Issued JOHNNY MIRANDA
Wood Frame 12/21/2021 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 1/19/2022 Approved JOHNNY MIRANDA
Insulation 2/2/2022 Approved KRISTEN CAUSEY
Drywall Nailing 3/3/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 3/3/2022 Partial Approval JOHNNY MIRANDA
Wood Frame 4/28/2022 Approved EVAN COOPER
Final 12/7/2022 Permit Finaled JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 12/7/2022 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 12/7/2022 Approved JOHNNY MIRANDA