3220 S MIDVALE AVE 90034
Certificate Information: 3220 S MIDVALE AVE 90034
- Application / Permit
- 20014-30000-05112
- Plan Check / Job No.
- B20WL05034
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior Remodel of (E) 1-Story S.F.D & (N) Open Deck (9'-1" x 25'-11 3/4")
- Permit Issued
- Issued on 9/10/2021
- Issuing Office
- Current Status
- Permit Finaled on 12/8/2022
Permit Application Status History
| Submitted | 11/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2020 | DAVID CASTILLO |
| Corrections Issued | 12/21/2020 | DAVID CASTILLO |
| Quality Review Completed | 12/28/2020 | TARIK SAOUD |
| Building Plans Picked Up | 1/4/2021 | APPLICANT |
| Applicant returned to address corrections | 5/5/2021 | DAVID CASTILLO |
| Applicant returned to address corrections | 6/8/2021 | DAVID CASTILLO |
| Applicant returned to address corrections | 7/13/2021 | DAVID CASTILLO |
| Plan Check Approved | 7/16/2021 | DAVID CASTILLO |
| Issued | 9/10/2021 | APPLICANT |
| Permit Finaled | 12/7/2022 | JOHNNY MIRANDA |
Permit Application Clearance Information
| Sewer availability | Cleared | 2/9/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2021 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 5/17/2021 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 5/18/2021 | KIRK LINKLATER |
Contact Information
| Contractor | Navarro Construction; Lic. No.: 1042757-B | 22412 MARBELLA AVE CARSON, CA 90745 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/5/2021 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2021 | Partial Approval | JOHNNY MIRANDA |
| Wood Frame | 11/30/2021 | Partial Approval | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 12/21/2021 | Partial Approval | JOHNNY MIRANDA |
| Special/Order Compliance | 12/21/2021 | Corrections Issued | JOHNNY MIRANDA |
| Wood Frame | 12/21/2021 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2022 | Approved | JOHNNY MIRANDA |
| Insulation | 2/2/2022 | Approved | KRISTEN CAUSEY |
| Drywall Nailing | 3/3/2022 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 3/3/2022 | Partial Approval | JOHNNY MIRANDA |
| Wood Frame | 4/28/2022 | Approved | EVAN COOPER |
| Final | 12/7/2022 | Permit Finaled | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 12/7/2022 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 12/7/2022 | Approved | JOHNNY MIRANDA |