3618 S CHESAPEAKE AVE 90016
Certificate Information: 3618 S CHESAPEAKE AVE 90016
- Application / Permit
- 20014-30000-05072
- Plan Check / Job No.
- B20WL05006
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of & addition to (E) garage to an ADU at rear of lot.
- Permit Issued
- Issued on 3/24/2021
- Issuing Office
- Current Status
- CofO Issued on 10/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2020 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 12/17/2020 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 12/22/2020 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 2/24/2021 | APPLICANT |
| Plan Check Approved | 3/10/2021 | VLADIMIR ARUTYUNYAN |
| Issued | 3/24/2021 | APPLICANT |
| CofO in Progress | 9/22/2022 | ANTHONY EGSON |
| CofO in Progress | 9/23/2022 | ANTHONY EGSON |
| Permit Finaled | 10/1/2022 | DEROLD HAUFF |
| CofO Issued | 10/1/2022 | DEROLD HAUFF |
| Permit Finaled | 10/1/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/14/2021 | RIDWAN HARDY |
| Address approval | Cleared | 1/27/2021 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 1/27/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 1/28/2021 | WALLIE JONG |
| Sewer availability | Cleared | 2/1/2021 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 3/1/2021 | JEREMY CARTER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/22/2021 | Approved | CALEB MEISTER |
| Excavation/Setback/Form/Re-Bar | 11/12/2021 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 12/17/2021 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 12/28/2021 | Approved | STUART CHAPMAN |
| Underground Mechanical | 2/22/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 3/3/2022 | Partial Inspection | ANTHONY EGSON |
| Green Building Rough | 3/3/2022 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 3/16/2022 | No Access for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2022 | No Access for Inspection | ANTHONY EGSON |
| Green Building Rough | 3/16/2022 | No Access for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 4/13/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 4/13/2022 | Approved | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 4/13/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 4/26/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 4/26/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Insulation | 4/28/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 4/28/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 5/2/2022 | Approved | ANTHONY EGSON |
| Insulation | 5/2/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 5/4/2022 | Approved | HORACE FULTZ |
| Interior/Exterior Lathing | 5/4/2022 | Approved | HORACE FULTZ |
| ELECTRICAL-Final | 6/8/2022 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Final | 6/15/2022 | Corrections Issued | ANTHONY EGSON |
| Final | 6/15/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 6/15/2022 | Approved | ANTHONY EGSON |
| Green Building Final | 6/15/2022 | Approved | ANTHONY EGSON |
| HVAC-Final | 6/15/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 6/15/2022 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 6/15/2022 | SGSOV Not Ready | ANTHONY EGSON |
| Smoke Detectors | 6/15/2022 | Approved | ANTHONY EGSON |
| Final | 6/17/2022 | OK to Issue CofO | HORACE FULTZ |
| SGSOV-Seismic Gas S/O Valve | 6/17/2022 | SGSOV Approved | HORACE FULTZ |
| Special/Order Compliance | 6/17/2022 | Approved | ANTHONY EGSON |
| Service/Power Release | 8/25/2022 | Approved | ANTHONY EGSON |